INTERCONNECTOR DAY35 MONAGHAN

EIRGRID ACCUSED OF BULLYING LOCAL PEOPLE AS INTERCONNECTOR ORAL HEARING ENDS

DAY THIRTY-FIVE

Closing submissions were made as the oral hearing entered its eleventh week

Michael Fisher  NORTHERN STANDARD  Thursday 26th May p.14

JAMES MCNALLY, Latnakelly, Anyalla, made his submission on Day 34. He said it would be an absolute travesty for the Board to approve such a poorly prepared planning application. His submission dealt with a section of the proposed route from where it would cross the border at Lemgare, near Clontibret, to Cornamucklagh. He said he had identified a number of discrepancies within the Environmental Impact Statement, but had received no credible answers.

He claimed the route selection process was flawed, by EirGrid choosing the “crooked elbow route”, through vulnerable elderly peoples’ property, adding a further 3km to the route and at least 11 or 12 additional pylons for which no rational or verifiable explanation had been provided. There would be a drastic negative impact over a considerable distance on the main tourist asset and local area of natural beauty, “The Monaghan Way” walk, he said.

Mr McNally claimed there had been avoidance of compliance with national and EU Legislation and habitats directives in relation to protected species such as the marsh fritillary butterfly and their habitat, bats, and badgers on the site of one of pylons. He claimed there was potential for the destruction of a nationally recognised site for rare orchids on the “Tassan grasslands”. He said there were three separate erroneous measurements on the distance of the proposed line from Tassan Lough national heritage area.

Regarding the presence of old mine shafts, Mr McNally claimed EirGrid had given no consideration to the risk for toxic lead, zinc, or arsenic run-off, into the ecologically sensitive Tassan Lough area and the potential for poisonous pollution to the local water table as a result of disused mine shaft collapse underneath two of the proposed pylons and other unidentified mine shafts in Lemgare and Annaglough. There was also the omission from the planning maps of a significant poultry unit in Lisdrumgormly. (EirGrid has already given its response on the mines issue, published last week).

EirGrid could not, and would not be allowed to force or coerce the people of Monaghan to accept an overhead powerline, he said. That was a fact that had been well established and emphasised by the numerous oral submissions at the hearing. No amount of posturing, or belittling, of the public submissions, would diminish the landowners’ resolve to have this powerline undergrounded. The community without access to experts, had spoken with one voice. He said it was now up to the inspectors to reflect that voice to the Board for its deliberations, however unpalatable it might seem to EirGrid.

CMAPC SUBMISSIONS

MARGARET MARRON of the County Monaghan Anti-Pylon Committee said for the last nine years since the project was first announced, the process pursued by EirGrid had been very stressful, annoying, frustrating and contrary to what would be expected of a publicly funded organisation. An organisation which she said had used taxpayers’ money arbitrarily to focus exclusively on their own narrow-minded objective, namely to build this powerline overground on pylons, with absolutely no regard for what the affected communities or their political representatives thought.

From the outset, the observers and public concerned, including the landowners, did not sense that procedural justice was high on the list in the oral hearing. Time limits were imposed on public participation and there were constant reminders that the process being conducted was “a fact-finding mission”, not an oral hearing on the application in front of the Board. The landowners were totally dismayed at the inaction of the inspectors in dealing with the “errata” identified in the EIS and the proposed modifications to route access points, the developer being allowed continually to improvise and amend the planning application throughout the hearing process.

CMAPC in association with NEPPC felt there was no alternative but to withdraw from a process which, in the eyes of the landowners, was flawed and biased in favour of the developer. We witnessed the developer being permitted, without hindrance or comment by the presiding Inspectors, to use the “fact finding mission” and information gleaned from the public submissions to address the deficiencies in the EIS and planning application, she said. The public therefore had a right to ask: where was the right to “access to justice in environmental matters” as stipulated in Article 1 of the Aarhus Convention?

Ms Marron continued: “Public hearings should not facilitate a “single-sided” approach while the opposition is absent, or where the public is unaware of the matters being proposed by the developer for acceptance by the Board. The only conclusion which the public can justifiably arrive at is that natural justice is being denied, and the whole planning process is therefore undermined. It could be easily construed that this whole planning process was just another ‘let some steam off’ or ‘tick the boxes’ exercise, designed to placate the public, while meeting the ever changing and seemingly flexible criteria of planning legislation to the advantage of the developer.”

She said it was incredible for the Board to allow a developer and its richly rewarded advisors blatantly to deny in public that there would be any health or life-changing impacts on vulnerable elderly people and mothers with autistic family members. She felt it was heart rending and shocking to watch private people who felt forced to outline their own personal family circumstances in a public arena. No attempt had been made to hold any of the public hearing “in camera” or in private, which was normal practice to accommodate people when issues of a sensitive nature were being considered.

She pointed out that throughout the oral hearing the developer had been seen to request the Board to ignore the established planning standards, regulations and laws, which had been strictly adhered to and implemented by planning authorities both at local and national level, and to allow the developer to carry out pre-construction verification surveys as a solution to their failure to carry out onsite surveys. This was not a solution which could be applied in drumlin topography and it had the added danger of setting a new precedent i.e. that established planning regulations could be totally ignored in future major development proposals.

The failings of desktop studies, aerial photography and LiDAR orthophotography were emphasised throughout the oral hearing process and were shown to be totally ineffective in identifying features on the ground. Some of the proposals provided by the developer to gain access over hedgerows and drains were farcical, totally inappropriate and bordering on the ridiculous.

The suggestions for transport of vast volumes of concrete and washing down of dumpers were equally absurd. The use of mini-diggers to gain access underneath enclosed hedgerows and rock surrounded entrances was impractical, yet the authenticity of such proposals was not questioned by the inspectors in most instances. Were members of the public present at the hearing expected to believe that what was being proposed by the developer was actually feasible, she asked.

In the opinion of the CMAPC, the EIS and planning application did not provide a neutral observer with objective, concise, and adequate detailed evidence to justify the destruction of a scenic unspoilt part of the Monaghan landscape. The developer had other options such as the use of more modern HVDC (High Voltage Direct Current) technology which could be put underground along existing infrastructural road networks which are owned by the state. The cumulative costs in terms of destruction of the unique drumlin landscape, the environmental and ecological destruction of protected species and habitats, the negative visual impact from a visitor and tourist perspective, the obtrusive overshadowing of national heritage assets, the increased risk to health and safety and possible fatalities underneath the proposed line, the decimation of house and land values along the alignment were some of the factors which in their view substantially outweighed the likely benefits of the proposed overhead 400kV power line.

The incompatible visual intrusion of industrial scale large steel pylon structures up to 52 metres high with the drumlin countryside would detract from the attractive rural character, appearance, amenity and setting of the landscape. It would be contrary to the proper planning and sustainable development of County Monaghan.

CMAPC were requesting the Board to consider the recovery of costs incurred by the public in this second planning application process and asking for a mechanism to be drawn up by the Board whereby the public and their advisors were reimbursed the fees incurred in participating in the “fact finding process” which had lasted over a number of weeks and months. People had endured considerable stress and emotional torment over an extended period during this entire planning process and were entitled at least to reimbursement of the direct costs associated with the hearing.

In conclusion Ms Marron said the anti-pylon committee had absolutely no doubt about the importance of Co. Monaghan to its residents and the devastating impact EirGrid’s proposal would have on their little bit of heaven. “We believe we do not inherit the Earth from our ancestors, we merely borrow it from our children and we want to ensure that future generations can inherit and enjoy the unique, unspoiled drumlin landscape, flora and fauna that we are fortunate enough to enjoy. We attended this hearing in good faith; we hope justice will prevail in the end and the Board will reject this planning application”, she said.

NIGEL HILLIS of the CMAPC referred to the government white paper on ‘Ireland’s Transition to a Low Carbon Energy Future 2015 – 2030’ launched in December 2015, which mentioned the need for the interconnector no less than six times. In para. 241 it stated: “The proposed North-South transmission line, which is currently in the planning process, will improve security of supply and reduce electricity transmission costs across the island”. Mr Hillis said it was implicit therein that the line would get planning permission. In his opinion this statement was tantamount to political interference and an attempt to finesse the planning process. It should be seen in that light by you and the Board, he told the presiding inspector.

The developer had stated over and over again that this project was needed for the economic development of the island of Ireland. As we have seen, it is of far greater economic importance to Northern Ireland than to us as they will supposedly run out of power in a few years’ time. So in the sense of economic development it was very much the case of the tail wagging the dog, he said.

Sustainable development in latter years had been very much driven by and embraced by climate change, he said. There had to be a compelling argument that undergrounding the project, which EirGrid’s CEO Fintan Slye had admitted was not only possible, but was also acceptable, was even more worthy of the title sustainable. It integrated and satisfied the three pillars of sustainable development: economic development, social equity and environmental protection. Undergrounding was in fact the most sustainable solution as it totally satisfied this triple bottom line of sustainability.

EirGrid had argued it would cost more to deliver the project underground and he accepted that the ‘nuts and bolts’ capital expenditure would be greater. But Mr Hillis said the affordability of undergrounding had never been examined because a full cost-benefit analysis had never been carried out.

Regarding access to lands along the route, it had been revealed that only 25% had been accessed and they did not even know where or what they are. There was no breakdown as to how much of the land accessed actually would have pylons, how much would have only the wires crossing and how much would be within 50 metres of the line, having neither pylons nor wires. Mr Hillis said in his view this was not proper planning. Indeed the withholding of such details was the antithesis of proper planning because properly informed comment could not be made by the public in the absence of this vital information.

This was now a project of common interest and the very highest standards must apply in both jurisdictions. If NIE or SONI walked into the Northern Ireland planning authorities with their application and said: we have only had access to 25% of the land for environmental surveys, I have no doubt they would be told to take the application away with them and shown the door, said Mr Hillis. In fact a “Consolidated Environmental Statement Addendum” was published in June 2015, the purpose of which was to provide the planning authorities with additional environmental information based on full access to 97% of the land in Armagh and Tyrone.

Mr Hillis noted that An Bord Pleanála had specifically requested that the NI planning documents and in particular the consolidated ES would be appended to EirGrid’s planning application. He requested that the inspectors and the Board took careful note of the huge difference in the quality of the environmental information, due mainly to the fact that 97% of land was accessed not once, but twice, in the N. Ireland section.

He then turned to his own area of expertise, namely construction, and a section in the Environmental Impact Statement regarding the requirement for temporary access tracks. It stated: “for the purposes of this appraisal, all temporary access routes have been assessed based on very wet weather conditions, expansive construction techniques with heavy machinery or equipment”.

Mr Hillis pointed out that only nineteen access points in Monaghan and Cavan and six in Meath were deemed to require temporary access tracks. This was totally ludicrous and nonsensical and was complete and utter guesswork and not evidence based on actual walk-over surveys in very wet weather, he said. He wondered what other areas of the EIS were totally deficient owing to the lack of proper on-site surveys at appropriate times of the year.

With regard to the so called mapping anomalies and incorrect capturing of roadside entrances, Mr Hillis claimed these were semantics in order to cover the fact that the roads had not been not driven on. He claimed the assessment was all done from out-of-date blurry large scale aerial maps on a computer, sitting in an office.

Again as more and more anomalies were brought to light by the landowners the machinery got smaller and smaller: mini diggers and mini piling rigs and concrete unloaded into dumpers ranging from 6 tonnes right down to 3.5 tonnes, the removal and double handling of spoil from sites, but yet the logistics for these operations had not been properly appraised at all. Mr Hillis said during the course of the hearing he had asked for a method statement to be prepared in order to understand better exactly what was entailed in this ever-changing construction methodology. But EirGrid’s barrister had immediately jumped to say that this would be going into excessive and inappropriate detail.

Mr Hillis continued: the Bob the Builder approach constantly taken by the developer (Can we fix it? Yes, we can) had no place at an oral hearing, in particular when the developer was a semi-state body which should have its planning application developed to the highest standards in all respects. The construction methodology had been totally revised in the course of the oral hearing and that section of the EIS was now, in his opinion, totally deficient and not fit for purpose.

He pointed out to the inspectors that in March 2016 an independent review group had published its organisational review of An Bord Pleanála. The review group was chaired by Gregory Jones QC who wrote in his foreword: “Planning is all about shaping the places in which we live. Planning decisions are not always easy. They involve judgements based upon balancing competing interests upon which people may have strongly held and divergent views. The issues are often complex and controversial.”

“The way in which planning decisions are taken also involves striking a balance between many factors. Some of these factors pull in different directions. We want planning decisions to be taken by people of integrity. We want decisions-takers to have fully considered the evidence and for their decisions to be soundly and carefully reasoned. We want everyone to have had a fair say.”

“Many challenges, such as, providing sufficient housing, securing sustainable economic growth, environment protection and addressing climate change, are shared by us all. In meeting these challenges countries can learn from one another. On the other hand, successful planning systems must also be fine-tuned to reflect the culture and values of the country and people they serve. One size does not fit all.”

The foreword by Mr Jones ends: “An Bord Pleanála enjoys a well-deserved high reputation for its integrity and professionalism. It is an internationally unique body playing a vital role in the planning system of Ireland. I consider it an honour and great responsibility to have been appointed to chair this Review.”

Mr Hillis addressed his closing remarks to the presiding inspector: “I don’t know, Madam Inspector, if you consider it an honour or not to have been appointed to this case or indeed if you simply just picked the short straw. But you do have a great responsibility, which cannot be abdicated, and I would ask you to dwell on those words of Gregory Jones QC. In particular, has everyone had a fair say at every stage of the process and does this application reflect the culture and values of the people that EirGrid are mandated to serve?”

“I ask you to give very careful and serious consideration if this strategic infrastructure application is indeed in accordance with proper planning and sustainable development in the linear area through which it is proposed to be sited. Whether that be the royal county of Meath, the intangible cultural areas of Loughanleagh and Muff in Cavan or the unique drumlins and scenic small lakes of Monaghan and indeed on the land of each and every landowner (big and small) on which it is proposed to be sited. I would respectfully submit to you that on the basis of the information gathered at this oral hearing it very definitely is not in accordance with proper planning and sustainable development.”

COLETTE MCELROY, Ballintra, again expressed concern about the proposed construction 475m from her house of a pylon with 400kV wires. She repeated her worries about the noise that would emanate from the lines, especially in wet weather and the impact the development would have on health.

EIRGRID have previously responded that during standard conditions there would be no significant noise emission from the overhead lines, but during wet conditions, corona noise might occur. The company said (using international standard methodologies) this noise was not predicted to cause significant impact at sensitive receptors. But for people with noise sensitivity, there was a need to consider this on a case-by-case basis.

MONAGHAN POLITICIANS

CAOIMGHÍN Ó CAOLÁIN TD, Sinn Féin deputy for Cavan-Monaghan, said the lives, hopes, plans and ambitions of people had been suspended in midair for the past nine years as a result of the application. If EirGrid thought the repeated statements that had been made favouring an underground route were a bluff, then let them call their bluff and they would see how strong the support was for undergrounding the interconnector.

He said the health risks from the proposed interconnector were real, as were the fears of local people. Over the past nine years the plans had caused stress on individuals, families and communities. He again raised concerns about the impact on the environment, on agriculture, on property and land valuation, as well as the effects it would have on tourism in the five coubnties affected.

He said his party was just one of the many political voices that had unanimously opposed the overhead lines. The EirGrid plan was also collectively challenged by the three County Councils in Monaghan, Cavan and Meath. An Bord must take note of their written and oral presentations on the project, he said. In 31 years as an elected representative he had rarely seen such a crass example of corporate bullying than had been demonstrated by EirGrid.

CLLR SEAN GILLILAND said the EirGrid application was “upside down” and it was the local community who had turned it upside down by showing its flaws especially regarding access routes and plans to build pylons on ground that EirGrid had not been able to access. He asked the inspectors and Bord Pleanála to let the people of Monaghan Cavan and Meath back to their normal lifestyle by rejecting the plan. The nature of the application was an insult to the people, to the inspectors and to the Board, he said.

Cllr Gilliland again claimed that photomontages produced by EirGrid at a number of locations were selective, using narow angle lenses so that in some cases the proposed pylons were hidden behind hedgerows, gateposts or road signs. On other occasions a wide angle lens had been used when it suited.

JOERG SCHULZE, the lanscape architect consultant for EirGrid previously pointed out in response to Cllr Gilliland and others that the photomontages had been taken at designated viewpoints on the public road. All had been produced in accordance with the relevant Landscape Institute guidelines for landscape and visual impact assessment.

NEPPC SUBMISSIONS

PADRAIG O’REILLY of the North East Pylon Pressure Campaign told the inspectors the EirGrid planning application remained invalid and should be rejected. Dr O’Reilly said multiple changes to the application that had been made during the eleven weeks oral hearing were an unacceptable waste of public monies. He said An Bord Pleanála had a duty not only to reject the application outright, but to direct that an appropriate alternative be considered for the future.

Dr O’Reilly said the application had been in the public domain for almost a year since it was submitted to An Bord Pleanála last June. In the past ten weeks the plan had been laid bare at the hearing. NEPPC which represented around 200 landowners mainly in Meath said its position in June 2015 was that this was an application so inadequate and deficient in so many aspects that it should never have been accepted as a valid application by the competent authority of An Bord Pleanála.

Now that the hearing was ending, the group’s position was that the application was even more inadequate, deficient and by default invalid than had originally been realised. The significant changes, errata, omissions and admissions made during the oral hearing were a testament to this invalidity and to the fatally flawed contents of the application. The legitimacy of the application and indeed of the applicant was therefore tarnished beyond redemption.

Dr O’Reilly said EirGrid to this day had refused to carry out the relevant analysis and costing of a site-specific underground high voltage DC cable solution along public roads. It followed from this fact that the planning application had failed to include an objective consideration of alternatives, and this fact alone should render the entire application invalid.

EirGrid was unaware of the latest publication from the European underground cable manufacturers representative body – Europacable – highlighting and proving their argument that an appropriate HVDC cable could easily be accommodated along the roads of the North-East. This publication had to be handed to EirGrid by the NEPPC.

According to the NEPPC, EirGrid’s blatant disregard for the whole process of consultation was on display at the hearing for the last ten weeks. Over fifty access route changes onto farmers’ lands were made during the hearing. No landowner notification, let alone consultation, occurred prior to any of these announcements. In fact the landowners affected by the first five announcements on Day One were never even informed until three weeks later.

There was a refusal by the company to make any attempt, such as public notices or other forms of media, to inform affected landowners promptly. There was also a refusal to put any of these changes on its website, until reluctantly consenting to do so at the very end of the hearing.

Significant changes had been made to the planning application during the course of the hearing. The Board had refused to clarify if these proposed changes were being accepted. This raised critical questions such as: why are significant changes to the planning application being entertained at this late stage? And why was there a refusal to date to clarify if the changes would be accepted?

NEPPC claimed EirGrid had taken an ‘a la carte’ approach to the planning application. For example there were now a series of options regarding access routes, guarding construction methods, concrete delivery methods, off-loading concrete, traffic movements and traffic management options, and a choice of forestry clearfelling, namely manual versus mechanical. This approach accoding to the group was contrary to all normal planning guidelines and instructions for the rest of the country.

The oral hearing process shone the spotlight on the glaring deficiencies in the Environmental Impact Statement (EIS). The only rational conclusion that could be drawn was that the EIS was so deficient as to render it impossible to arrive at an adequate Environmental Impact Assessment (EIA).

The NEPPC pointed out that EirGrid was unable to access at least 75% of the lands for which it intends to construct over 300 massive pylons. The Environmenal Impact Statement was thus 75% deficient in detailed site-specific information on such critical aspects as flora and fauna and soil geology. Finally, EirGrid had interviewed only 5% of the landowners on whose lands it required access and co-operation. For these reasons, Dr O’Reilly said, the Board had a duty not only to reject the application outright, but to direct that an appropriate alternative be considered for the future.

AIMÉE TREACY, Chairperson of the NEPPC, spoke on behalf of concerned residents groups in Co. Meath. She said EirGrid had given no prior notice nor had they been in consultation with landowners before they made more than fifty changes to the original planning application, most of them alternative access routes for construction. She described the application as deeply flawed and claimed it was invalid. It would never be accepted by the public, she said. Her contribution was applauded by the large crowd of observers.

Dr COLIN ANDREW of the NEPPC said the EirGrid application had been catastrophically flawed from the outset. EirGrid representatives had prevaricated and filibustered and refused to give straight ‘Yes’ or ‘No’ answers to questions raised by observers. He said the application had not shown that there would be any benefit to the electricity consumer by building the interconnector.

MEATH POLITICIANS

PEADAR TÓIBÍN TD Sinn Féin deputy for Meath West said the Board now had an opportunity to put the rights of citizens and of the community at the centre of the planning process. He claimed EirGrid were stealing equity away from families by attempting to put pylons on their property.

REGINA DOHERTY TD, government Chief Whip and Fine Gael deputy for Meath East called on An Bord Pleanála when making their decision to take into account the impact the plan would have on real lives, which she said could not be underestimated. She said that EirGrid had behaved with what could only be described as arrogance, and with very little respect for the public, the affected communities and landowners.

She told the inspectors it was almost exactly ten years since she first attended a public meeting in Trim, organised by the NEPPC, for the initial proposal for the North-South interconnector. “I find it incredibly difficult to fathom, exactly how EirGrid, ten years later, have made so many last minute, but substantial, changes to their planning application, despite having had six years since their initial application to An Bord Pleanála”, she said.

Ms Doherty continued: “For the second time, we have seen a planning application from EirGrid which is inherently flawed, in the form of what one can only assume to be carefully choreographed changes to fifty access routes, which have left both members of the public, and affected landowners, completely in the dark. As a result, we have been left unable to engage with these changes. I am reliably informed that some affected landowners have not even been notified by EirGrid as to these changes, despite EirGrid stating otherwise.”

“EirGrid, has essentially robbed Meath landowners and communities from being able to partake in what should have been a thoroughly democratic and transparent public consultation. I also share the confusion which was voiced in the room as to whether the Board will be adjudicating upon this planning application either with, or without, the extensive amendments to access routes presented by EirGrid.”

Ms Doherty said in conclusion: “I again echoed the striking absence of a fully costed alternative undergrounding, or partial undergrounding, of the interconnector, which, in and of itself, most are in agreement is a much needed upgrade to our critical national infrastructure. We cannot, and will not, take EirGrid on its word, that undergrounding is not feasible for long-term viability and sustainability reasons.”

 GOVERNMENT WHITE PAPER

KEVIN BRADY, Principal Officer in charge of Strategic Energy Policy at the former Department of Communications, Energy and Natural Resources, said a white paper on energy (Ireland’s Transition to a Low carbon Energy Future) was published in December last year, setting out a vision and framework for energy policy from 2015-2030. He said Ireland valued its relationship with Northern Ireland including energy matters and they were part of an all-island electricity market. Mr Brady said the need for an appropriate energy infrastructure including interconnectors underpinned all energy policy. But the government was not seeking to determine specific details of the interconnector scheme or to direct EirGrid about particular sites, routes or technology.

A second interconnector would fulfil the three core energy policy requirements of competitiveness, security of supply and sustainability. The proposal had been designated as an EU project of common interest. They needed to ensure there was access to wider markets and both Ireland and Northern Ireland would benefit from security of supply by having a single system across the island, Mr Brady said.

EIRGRID CLOSING SUBMISSION

BRIAN MURRAY SC for EirGrid set out the reasons why a second North-South overhead interconnector was required. It was necessary to overcome the risk of system separation and to increase transfer capacity between the two electricity transmission systems on the island. It would help achieve the objectives of improving market competition in the context of the Single Electricity Market, to support the development of renewable power generation and to improve security of supply. “These are absolutely critical objectives”, he said.

Mr Murray re-stated the support for the proposal which had been voiced by government in its white paper on energy and other key stakeholders who had made presentations at the hearing. “Garrett Blayney of the Commission for Energy Regulation said that there was a ‘clear and pressing need for the construction of the interconnector as quickly as possible and in a cost efficient manner’. Mr Owen Wilson of the Electricity Supply Association said that ‘failure or delayed delivery of the North- South Interconnector risks significant damage to Ireland’s national interest’.”

“Mr Neil Walker of IBEC gave evidence that IBEC wished to see the interconnector proceed as proposed, as it will be of real benefit for all electricity users and the wider economy. Mr Iain Hoy of the Northern Ireland CBI said that successful construction was ‘vital to protect security of existing supply, facilitate competition of SEM and reduce costs’. Similar evidence was given by Mark O’Mahoney of Chambers Ireland.”

EirGrid’s closing statement outlined the requirement for an overhead, 400 kV Alternating Current (AC) interconnector. Mr Murray said the use of Direct Current (DC) as opposed to AC current had been considered. A DC option would not provide the same level of reliability and security of supply as an AC solution. A DC solution would be suboptimal. The complexity of the system required to accommodate a DC link introduced a big risk that things could go wrong, as Project Manager Aidan Geoghegan had explained. There was no example of a comparable HVDC scheme embedded in an AC system.”

EirGrid’s view was that the proposed 1500MW capacity was required in order to provide adequate contingency in the event of a failure of the existing interconnector. It was also necessary to provide sufficient additional capacity to allow the longer term sustainable development of the network as demand for electricity grew both in the region and on the island of Ireland.

Mr Murray continued: “Cost is certainly a relevant and important consideration. EirGrid is mandated by statute to develop the national grid in a manner that is safe, secure and cost effective. A DC underground cable would cost €670m more than the proposed AC overhead line”. However, contrary to what had been said repeatedly at the hearing, cost was not the only consideration.

“It is not technically feasible to underground the entire interconnector using AC cable. This is because the distance is simply too great for an AC underground cable of the size and power carrying capacity required for this project to operate safely”, the lawyer for EirGrid explained.

Mr Murray also spoke of the environmental considerations in the proposal. “The potential for impacts on designated European sites (River Boyne and River Blackwater) have been comprehensively assessed in the Natura Impact Statement. It has been clearly established that no structures or works will be located within these or any designated European sites. Mitigation by avoidance at the design stage, in addition to effective and proven robust mitigation measures, must lead to the conclusion that there will be no impacts on the integrity of any designated Natura 2000 site.”

Regarding the level of public consultation carried out as part of the project, Mr Murray said “this project has been the subject of exhaustive consultation. It is not and never was a ‘box ticking’ exercise. It is something viewed by EirGrid as central to the future of the project.”

Mr Murray addressed the issue of temporary access routes, which had been raised on several occasions during the hearing. “The access routes do not form part of the development. Therefore, no part of the development has changed in any way in the course of the hearing. The access routes are included as part of the Environmental Impact Statement (EIS). For that reason, EirGrid has quite properly taken account of information gathered in the course of that process.”

“It is in this context that EirGrid brought a number of access routes to the attention of the attendees at the hearing in order to enable the Board to assess the modifications proposed to those access routes. These have been advised to affected landowners.”

EirGrid said it had considered all potential deviations or mapping discrepancies, whether those issues arose from the EIS access route mapping or the larger-scale landowner mapping. The review process had revisited aerial imagery, landowner access mapping and EIS figures with follow-up vantage surveys, as necessary, according to Mr Murray.

He concluded: “EirGrid submits that the second North-South interconnector is a project which is critically necessary. It is a project which we believe can only be sustainably developed in the manner proposed, and it is a project which minimises adverse impacts to the greatest extent possible.”

Referring to the court case brought by the NEPPC seeking to halt the oral hearing, Brian Murray SC said the inspectors would recall that on the eve of the hearing, some observers sought to halt it, and repeated that application before the hearing. Thus on Thursday May 12th, just as the submissions were concluding, the High Court delivered its judgement on the application for leave to seek judicial review.

The High Court determined, effectively, that the various grounds which had been raised before it were (save for PCI) in the first instance matters properly for An Bord Pleanála to determine rather than for the High Court. Mr Murray said that did not preclude a judicial review on those grounds following a decision of the Board if the application was granted. But it did mean that it was the Board which must decide those issues first, on the basis of the facts and evidence it has before it.

The application to build a 400kV overhead line with almost 300 pylons stretching 135km from Meath to Tyrone was made to the Board in June last year. It has been examined in detail at the oral hearing that began in March and lasted 35 days. It was one of the biggest ever such enquiries into what is said to be the largest single infrastructure development in the state in recent years. The inspectors will now prepare a report for the Board, which is expected to announce its decision towards the end of this year.

A preliminary hearing under the auspices of the Planning Appeals Commission in Northern Ireland will take place in Armagh next month. This first stage will discuss legal and procedural issues surrounding the SONI application for the 34km section of the interconnector with 102 pylons from Crossreagh, Co. Armagh (near Clontibret) to Turleenan near the Moy in Co. Tyrone, where a substation is due to be built.

INTERCONNECTOR DAY35

EIRGRID DEFENDS INTERCONNECTOR PLAN AS ORAL HEARING ENDS

Michael Fisher

EirGrid has been accused of bullying and of showing disregard and disrespect for landowners, famers and residents in Meath, Cavan and Monaghan affected by the company’s plan to build a second North/South electricity interconnector. Government Chief Whip Regina Doherty TD (Meath East) along with two Sinn Féin TDs were among a dozen people (including EirGrid) who made closing submissions to the two inspectors at an oral hearing in Carrickmacross. Ms Doherty called on An Bord Pleanála when making their decision to take into account the impact the plan would have on real lives, which she said could not be underestimated.

The application to build a 400kV overhead line with almost 300 pylons stretching 135km from Meath to Tyrone was made to the Board in June last year. It has been examined in detail at the oral hearing that began in March and lasted 35 days. It was one of the biggest ever such enquiries into what is said to be the largest single infrastructure development in the state in recent years.

Sinn Féin Meath West TD Peadar Tóibín said the Board now had an opportunity to put the rights of citizens and of the community at the centre of the planning process. He claimed EirGrid were stealing equity away from families by attempting to put pylons on their property.

His party colleague from Cavan/Monaghan Caoimghín Ó Caoláin TD said the lives, hopes, plans and ambitions of people had been suspended in midair for the past nine years as a result of the application. If EirGrid thought the repeated statements that had been made favouring an underground route were a bluff, then let them call their bluff and they would see how strong the support was for undergrounding the interconnector.

The anti-pylon group North East Pylon Pressure Campaign told the inspectors the EirGrid planning application remained invalid and should be rejected. Dr Padraig O’Reilly said multiple changes to the application that had been made during the eleven weeks oral hearing were an unacceptable waste of public monies. He said An Bord Pleanála had a duty not only to reject the application outright, but to direct that an appropriate alternative be considered for the future.

Now that the hearing was ending, the group’s position was that the application was even more inadequate, deficient and by default invalid than had originally been realised in June 2015. The significant changes, errata, omissions and admissions made during the oral hearing were a testament to this invalidity and to the fatally flawed contents of the application. The legitimacy of the application and indeed of the applicant was therefore tarnished beyond redemption.

NEPPC claimed EirGrid had taken an ‘à la carte’ approach to the planning application. For example there were now a series of options regarding access routes, guarding construction methods, concrete delivery methods, off-loading of concrete, traffic movements and traffic management options. This approach according to the group was contrary to all normal planning guidelines and instructions for the rest of the country.

Margaret Marron of the County Monaghan Anti-Pylon Committee claimed EirGrid, a semi-state company, had used taxpayers’ money arbitrarily to focus exclusively on their own narrow-minded objective, which was to build the power line overground on pylons, with absolutely no regard for what the affected communities or their political representatives though.

Ms Marron said to allow a developer and its richly rewarded advisors to deny blatantly in public there would be any health or life-changing impacts on vulnerable elderly people and mothers with autistic family members was incredible. It was heart- rending she said to watch private people who felt forced to outline their own personal family circumstances in a public arena; it was shocking to those present. No attempt was made to hold any of the public hearing “in camera” or in private, which is normal practice to accommodate people when issues of a sensitive nature were being considered.

Nigel Hillis of CMAPC submitted that undergrounding was the most sustainable solution. The developer had argued that it would cost more to deliver the project underground and his group accepted that the ‘nuts and bolts’ capital expenditure would be greater. But the affordability of undergrounding had never been examined, he said, because a full cost-benefit analysis had never been carried out.

Mr Hillis said the construction methodology for the pylons and lines had been totally revised in the course of the oral hearing. That section of the Environmental Impact Statement was now, in his opinion, totally deficient and not fit for purpose. He went on: “the Bob the Builder approach constantly taken by the developer: Can we fix it? Yes, we can, has no place at an oral hearing and in particular when the developer is a semi-state body who should have its planning application developed to the highest standards in all respects.”

Dr Colin Andrew of the NEPPC said the EirGrid application had been catastrophically flawed from the outset. EirGrid representatives had prevaricated and filibustered and refused to give straight ‘Yes’ or ‘No’ answers to questions raised by observers. He said the application had not shown that there would be any benefit to the electricity consumer by building the interconnector.

Kevin Brady, Principal Officer in charge of Strategic Energy Policy at the former Department of Communications, Energy and Natural Resources, said a white paper on energy (Ireland’s Transition to a Low carbon Energy Future) was published in December last year, setting out a vision and framework for energy policy from 2015-2030. He said Ireland valued its relationship with Northern Ireland including energy matters and they were part of an all-island electricity market. Mr Brady said the need for an appropriate energy infrastructure including interconnectors underpinned all energy policy. But the government was not seeking to determine specific details of the interconnector scheme or to direct EirGrid about particular sites, routes or technology.

A second interconnector would fulfill the three core energy policy requirements of competitiveness, security of supply and sustainability. The proposal had been designated as an EU project of common interest. They needed to ensure there was access to wider markets and both Ireland and Northern Ireland would benefit from security of supply by having a single system across the island, Mr Brady said.

EIRGRID CLOSING SUBMISSION

EirGrid as the applicant was given the last word to explain why a 400kV alternating current (AC) overhead interconnector was a key part of Ireland’s energy future. A lawyer for the company Brian Murray SC said the proposed infrastructure was necessary to overcome the risk of system separation and to increase transfer capacity between the two electricity transmission systems on the island. It was required to achieve the absolutely critical objectives of improving market competition in the context of the Single Electricity Market, to support the development of renewable power generation and to improve the security of supply.

Mr Murray said the use of Direct Current (DC) as opposed to AC current was considered. A DC option would be suboptimal as it would not provide the same level of reliability and security of supply as an AC solution. He said there was no example of a comparable HVDC scheme embedded in an AC system. Mr Murray also spoke of the environmental considerations in the proposal.

On public consultation carried out as part of the project, Mr Murray said “this project has been the subject of exhaustive consultation. It is not and never was a ‘box ticking’ exercise”. Mr. Murray addressed the issue of temporary access routes, which was raised on several occasions during the hearing.

He said the access routes did not form part of the development. Therefore, no part of the development had changed in any way in the course of the hearing. The access routes had been included as part of the Environmental Impact Statement (EIS). For that reason, EirGrid had quite properly taken account of information gathered in the course of that process.

It was in this context, he said, that EirGrid brought a number of access routes to the attention of the attendees at the hearing in order to enable the Board to assess the modifications proposed to those access routes. These had been advised to the affected landowners.

Mr Murray concluded “EirGrid submits that the second North-South Interconnector is a project which is critically necessary. It is a project which we believe can only be sustainably developed in the manner proposed, and it is a project which minimises adverse impacts to the greatest extent possible.”

The inspectors will now prepare a report for the Board, which is expected to announce its decision later this year.

 

 

INTERCONNECTOR DAY26

DAY TWENTY-SIX

This section involved landowners and groups from Co. Monaghan

SEAN DUFFY, Drumguillew Lower, was represented by his mother Mary Duffy as he is in Australia at the moment. He had inherited ten acres of land from his uncle in February 2011. There had been no contact with EirGrid about their plans to build two pylons and a power line near the dwelling house. Mrs Duffy said there was also a plan to put two pylons on her daughter’s land at Drumhowan, one of which EirGrid had now moved across a ditch onto a neighbour’s land.

NIGEL HILLIS of the County Monaghan Anti-Pylon Committee said there could have been another technical solution without moving that particular pylon. He claimed that EirGrid had been in breach of the Aarhus Convention on public consultation and EU directives. The proposed line design stretched back to 2011 and was followed with a preferred solution report and then a final line design that the EirGrid board had approved according to the Chief Executive. The company had years to get it right and after all this they had decided to move eleven of the pylons on the proposed route when the planning application was submitted last year.

BRENDAN MARKEY, Greagh, was represented by Sean Gilliland. He did not want pylons on his land. Cllr Gilliland said the proposed access lane for construction of two pylons on Mr Markey’s land was only 8’6” wide with a water pipe below it and two other pipes alongside. It would most certainly be damaged if heavy machinery used it.

The lane was very special as there were visible badger tracks and badger setts that were monitored by the Department of Agriculture and NPWS. The power line would be a ruination of the rural countryside and way of life.

GABRIEL MOONEY, Greagh, was joined by his father Bernard in making a submission. They had huge concerns over the project. They lived 200m up a lane that EirGrid planned to use to access one of the pylons for construction. The lane was in frequent use by family members daily and they would be disrupted if heavy machinery was going to use the lane. He asked who would be responsible if there was an accident on the lane, or if it gave way under the heavy loads that would have to pass along it. Could EirGrid guarantee the safety of his young children while the proposed work was taking place? He also wondered if the company could guarantee that they would not in their lifetime experience any health effects from living beside the proposed high voltage lines.

He expressed concern that their homes and properties would be devalued and worth next to nothing in future. Nobody would want to live near these grotesque pylons, he said. The lines would destroy totally the aesthetic appearance of their locality.

He concluded: “We are all proud Irish people, proud of our democracy. We have the power to elect our public representatives; we have the power to decide if there are changes to our Constitution. We express our democratic right by voting and we accept the outcome. The people of Monaghan, Cavan and Meath had voted unanimously against this overhead power line. EirGrid should accept this fact and scrap this proposed project”.

LEO MARRON, Greagh, said the pylons would be an attack on our freedom to live according to our own traditions and own choices, currently and into the future. We could no longer sell our property or hand it onto the next generation. We could not develop it as a viable enterprise and make more of it as previous generations did.

I left my parcel of land with an estate agent in February and told him to be open and honest with all inquiries. The land was advertised locally and internationally but there have been no offers. Such is the mistrust that EirGrid have instilled among the people of our community that I took the land off the market as we feared EirGrid would use the opportunity to walk the land and gather information for their own purposes. I have no doubt that the threat of this pylon has affected the value of my land and other properties in the local area.

I face particular challenges with a disability that means I must meticulously plan my work days and weeks ahead and ensure I have adequate support to carry out my daily duties. EirGrid interference would interrupt this planning., becoming another obstacle I could live without and making farming almost impossible for the duration of the construction. The two months stated by EirGrid are only the tip of the iceberg though, as there will be continuous interference by EirGrid for a further three years and ongoing into the future. This will undoubtedly be the end of my way of life.

I have worked for years to increase the productivity of my land, digging shores to dry the land. Still it is soft in places and heavy construction would damage these land drains and undo the work I have laboured so hard over. Can EirGrid inform us here as to the weight of the pylons and measures they would take to mitigate the damage caused to my land? Or are EirGrid even aware of these factors? It appears that EirGrid have not properly assessed the land and have no idea really as to the possible consequences of building a huge pylon in my field. Also I wonder are EirGrid aware of the dangerous blind spot that exists on this apparently straight stretch of road? All households here are aware of how devious this stretch of road is. The heavy construction vehicles and increased traffic that EirGrid will bring will compound factors and make a fatal accident all the more likely. EirGrid have boasted of their strict timetabling of construction. This evidently could place pressure on contractors to reach deadlines and take short cuts on health and safety: which should come first? With so many homes surrounding the construction site I do not trust EirGrid to put the interests of families and children first. Rather it seems that profit and scheduling comes before the people and community. I wish to draw to your attention an article in the Farmers Journal dated October 11th 2014 which described the ESBs laissez-faire approach to pole removal that damaged a contractor’s harvester and left a hole in his pocket. It seems to me that EirGrid’s approach to planning and execution of these pylons will be no better and could leave many farmers out of out of pocket due to similar damage caused. EirGrid have forfeited all confidence in their abilities and no farmer would agree to allow them onto their land to destroy it.

The field on which EirGrid plan to construct this pylon is flat and poses a real and significant eyesore to a number of neighbours. It is cruel and unfair that their homes too should suffer the indignation of this towering pylon and the loss of value to their homes. To EirGrid this is all business and nothing personal but to us it’s very personal.

I also have more land in Ardragh where I am being affected by construction between pylons 190 and 191. The shared lane serves many farms and homes and as such heavy vehicles would pose a significant risk. Damage to the surface of the lane would be inevitable and have unfair and lasting consequences for those who rely on it. Furthermore there is a well that is under the lane which has historical significance that leads back to the famine era and has been minded for generations. I have an uncle who will turn 100 this year and used this well for drinking water from a child. Heavy vehicles would destroy this important piece of heritage and history and I doubt EirGrid are even aware of its existence. There are in fact several other errors in the proposed plan I could point out to EirGrid, but I would feel foolish pointing them out to such educated men.

ANN MCARDLE, Brackley, was represented by her son COLM MCARDLE. He said they were not happy about having pylons on their land. In their original application EirGrid had proposed an access route for construction that went through an embankment onto the pylon field. The access was then changed through their back yard. They wondered how this would affect the milking of cows and moving them around the farm.

BYRNE FAMILY, Brackley

Briege Byrne said the family home sits between proposed Pylon 162 and Pylon 163, The overhead power lines would run for 80 metres along our land and right over our sheep’s house. The overhead power lines will be 62.5 metres from our family home. This is the only land parcel we own and it is home to our livestock.

EirGrid wants to access our land to facilitate stringing of the overhead power line – they do not have our permission to enter our land.

EirGrid wants to use our private entrance to access our land with large, heavy construction machinery. They will have great difficulty navigating in a slope, off a busy main road, on a bad bend; onto wet boggy soft ground all year round which floods regularly.

Quote from EirGrid:

“The 0.7 hectare land parcel with beef enterprise is located in Brackley Co. Monaghan. The sensitivity is medium. There is a yard/farm building located approximately 30 meters north west of the proposed overhead power lines”.

The land parcel is not 0.7 of a hectare; it is only 0.5 of a hectare of land. The farmyard/building is not 30 metres from the overhead power lines it is right under the power lines.

EirGrid propose that they will need 65 metres of an access track to facilitate stringing of overhead Power lines at a loss of 10% of the land parcel. “Pre-mitigation the impact is moderate adverse”.

We use our field by split grazing, so the field is divided in half. The half EirGrid wants to access has our sheep’s house – which will have the overhead power line running over it – and is used to summer graze if possible as this is when it is at its driest, although our sheep will be rotated on it all year round as required.

“The construction disturbance impact is short term (generally less than 12 months) the magnitude of construction impact is low and the significance is slight adverse”.

How can EirGrid say it is short term? This is our home, our lives, our animals; the impact has already commenced and shall be engraved on the land for an eternity. EirGrid want access for 12 months. How are we going to split graze? How are we going to feed our sheep? How are we going to access our sheep’s house? To say the impact is low is hurtful and demoralising.

EirGrid say “There will be a low level of disturbance”.

This is not a true reflection. There will be a high level of disturbance. When EirGrid are finished we will be unable to use our field, we will be unable to feed our sheep, we will be unable to house our sheep and after 12 months of large heavy construction machinery, the land will be more like a building site than a grazing field – it will be ruined and we will be left with our home 62.5 metres from the overhead power line with a view of pylon 162, Pylon 163 and Pylon 164. We have 80 metres of overhead power line on our land, land we cannot use, left sterile due to the health risks this poses on us and our animals along with the constant humming and cracking sound of the overhead power lines. We see all of this as a high level of disturbance.

“There is a high impact on farm buildings and their potential expansion due to location of power lines 30 metres from yard”.

Our farm building is our sheep’s house and it is right under the power lines, this means our sheep cannot be housed in this area. Where shall we house our sheep as we only have a small parcel of land, which means we cannot build on our land.

“The impact magnitude is high and the significance of the residual impact is moderate adverse”. This overhead power line will have an immediate and detrimental impact on our health and the value of our home and land. EirGrid say this will have a low environmental impact. How can they say this? They have not stood on the land and how can they say what the environmental impact an overhead power line will have?

“Hedges land trees may be cut back within 30 metres of the overhead power lines”.

What about the hedgerow on our land? The power lines shall be running over this hedgerow. The hedgerow is home to wildlife and offers a feeding ground for many lives such as birds and bats. The river beside our land runs alongside this hedgerow. What about all the fish and creatures in the water? How can anyone say that there will be a low environmental impact when hedgerows shall be removed and rivers disturbed?

As well as the ground animals and birds we must also look up and realise that we are also on the flight path for swans and ducks. Just over the field from our home lies Barraghy Lake. The swans and ducks fly back and forth on a regular basis. These wires shall be in their direct flight pathway. We are worried that these birds may end up in the wires.

In short this is our field gone, our land gone, no grazing for our sheep, no roaming for our hens, the hedges gone: which has a knock-on effect – no birds, bats rabbits to name a few – the river that runs along the hedge tampered with and in effect gone.

What about our health and the health of our livestock? Our sheep are so close to this overhead power line. How can we be sure they will be safe? Could this cause the sheep to miscarry, have lambs born with deformities? Also our hens roam freely through the field. What about their wellbeing? They supply the family home with eggs – will we be able to keep our hens? Will we be able to consume their eggs? Our spring well is 50 feet from the overhead power lines – can we still use this water? These questions highlight that the environmental risk is high rather than low.

My child visits the family home on a regular basis. How can I visit the family home knowing that I run the risk of putting my child’s health at risk for e.g. leukaemia and other disorders? I cannot do this to the next generation.We should be protecting them not putting them at risk. Life is precious and should be cherished not put at risk because EirGrid want to erect pylons.

Along with my child’s physical wellbeing I am also extremely concerned about the physical and mental wellbeing of my parents, they have reared their children and put a lot of time and love into building a safe environment for me and my siblings and for us to be able to bring our children back to the family home, but this will be shattered. From the day that talk of this interconnection commenced it has had an impact on our emotional wellbeing. We are upset and stressed due to the possible erection of this interconnection. We will have nothing left by the time EirGrid are finished. We also need to be aware that there is a physical strain placed on every single person who is here today and is affected by EirGrid’s proposals. We can see the physical strain on people. We also need to be mindful of the mental strain this project is placing on people; this is very concerning as we sit and listen to families plead for their lands to be left untouched. We are getting a taste of how people feel as we listen to the stories of how a power line can rip through a person and put them under emotional and physical strain. Is it worth putting people under this pressure and strain? The answer is NO!

PEADAR CONNOLLY, Chairman of Lough Egish Community Development Company Ltd that runs the Food Park said overhead pylons would have a detrimental effect on the wellbeing of all in the Aughnamullen community. He explained the history of the food park which he said provided food to people from all corners of the island, from meat to dairy to eggs and dry foods. He pointed out that he had difficulty accessing any environmental impact statement on EirGrid’s web page.

(This was immediately checked by the company’s representatives who told the inspectors all the relevant EIS information had been put on a dedicated website set up at the request of An Bord Pleanála and which was found to be working properly).

Mr Connolly said he was extremely concerned about the adverse effect the overhead power line would have on the food park and the livelihood of local people. EirGrid, he claimed, had failed to demonstrate the safety distance for the food industry and employees regarding EMF emissions from 400kV power lines. He feared that a stigma might arise from the location of their food products not far from the high voltage cables and once it arose then they would be out of business. It was a risk he was not willing or able to take. He urged An Bord to ignore any pressures that might be exerted on them to fast-track the proposed project and to be mindful that the health and wellbeing of all citizens in the affected areas and generations to come were in their hands.

INA and CHARLES HEGAN, Brackley, made a submission in which they said the EirGrid plan would have a number of disastrous consequences for their farm, house, family and livestock. One pylon would be close to the front of their house. There would be a severe visual impact. There would be an immediate and detrimental effect on the value of their farm. The overhead cables would create a substantial risk to using farm machinery. There had been no proper consultation with them, she said.

DOMINIC HARTE, Brackley, also expressed concern about devaluation of his home and property and the visual impact of the pylons. He also questioned whether sufficient provision had been made for flight diverters on the power lines to take account of the flight paths of wildlife at two local lakes. He also enquired about the procedure that would be used for inspecting the power lines, if they got approval.

MICHAEL HALPIN, Barraghy, was represented by Briege Byrne. My home sits between pylons 163 and 164. The power line will run on the edge of my land. EirGrid propose to access pylon 164 by using a lane which is owned by my neighbours Mr and Mrs Charlie Hagan. This lane runs parallel with my own driveway and on past the front door of my house into Mr Hagan’s field where pylon 164 is to be erected. This lane is not capable of taking heavy farm machinery as it is soft ground that runs along a river. From the picture you will see that the edge of the lane which is not defined by a hedgerow is about 4 feet from my front door. This would pose a serious problem for EirGrid. How do they propose to turn in off the road on a bend, go up a soft narrow lane 4 foot from my front door with heavy construction machinery? It is not possible. The machinery would be rubbing off my porch, I would not be fit to use my front doorway. EirGrid will need to cut down my mature trees which are very close to my house. These mature trees are home to a lot of wildlife and bats. This is not acceptable.

Over the last number of years I have spent a lot of time and money updating my house and land. These pylons and overhead power lines are so close to my home that both my home and my land would be worthless, devaluing everything I have worked for. It would leave living in my own home very hard due to the impact on my health and wellbeing.

PAURIC CONNELLY, Barraghy, was represented by Sean Gilliland. EirGrid had not convinced him that there was no medically adverse activity arising from the pylons. The proposed line would be a desecration of the landscape.

Cllr Gilliland asked if EirGrid could inform the hearing how much his land would be devalued if the project was allowed. He had very real concerns and wanted to know if he would get planning permission for any sites to provide new homes if they were near the power lines.

EILEEN MCGUIGAN a neighbour said her home was her castle. She had six grandchildren and was concerned about possible health hazards if a pylon was built nearby. “No pylons—NO-NO-NO!” she stressed. She was applauded as she concluded.

PHIL GEOGHEGAN, Drumillard, was represented by Sean Gilliland. Mr Geoghegan shared access to his holding with seven other people. It was a private lane and they had all contributed to tarring it and contributing to the upkeep. If damage was caused by contractors’ traffic using the lane for access to a pylon construction site, he wanted to know who would pay for it? Mr Geoghegan was totally and utterly opposed to the proposed pylon on his land. Cllr Gilliland pointed out that there were already three power lines crossing his farm and now there could be seven or eight. There would not be much room left on his land holding. He also mentioned that problems had arisen regarding compensation at another infrastructure development in the county.

PATRICK MARRON, was also represented by Sean Gilliland.

Mr Marron, a farmer, had not received any information to date from EirGrid regarding a plan to use part of his land as a guarding location for one of the pylons. He was anxious about this and wondered how EirGrid had managed to put in a planning application without conculting the person who owned the ground for the planned tower. Cllr Gilliland also pointed out that the proposed access route belonged to someone else, a Mr Connolly (see below).

ROBERT ARTHUR of ESB International said in many instances access to pylons went across third party land. He would endeavour to get the details regarding that particular holding.

SEAN GILLILAND pointed out that this landowner was known to EirGrid as maps had been sent to him regarding the previous application. So the company was very well aware of the owner. There had been correspondence with Mr Marron in December 2013, so this was not a case where EirGrid was not aware of who owned the parcels of land.

PATRICK CONNOLLY, Tooa, a landowner, told the hearing he had not received any communication from EirGrid regarding a proposed access route to pylon 170 on the land of the Ward family. When this divergence of opinion became clear a coffee break was called by the presiding inspector.

Upon investigation, EirGrid lawyer Jarlath Fitzsimons said a letter had been sent by tracked mail to Damian and Patrick Connolly on 29th May 2015. It was delivered on to an address at Tooey, Shantonagh, Castleblayney at 9:31am on 4th June 2015, according to a postal track and trace.

Cllr Gilliland said it was strange that a separate letter had not gone out to the two names on the holding, if two parties were involved. He continued to press for information about the proposed access routes that were being used to pylons. One of them, he said, was so overgrown that you could not even wheel a wheelbarrow in there, let alone deliver any concrete unless it was in a bucket.

Following this exchange EirGrid introduced new information regarding seven access routes and eleven minor changes arising from map inaccuracies.

JARLATH FITZSIMONS SC for EirGrid said the application before the Board was for an overhead line and there was no proposal to underground the line. Let’s be clear about it, he told the inspectors. He also said a number of issues raised regarding land valuation, health and tourism had already been answered in previous modules.

INTERCONNECTOR DAY9

This section dealt with construction, including temporary access routes

At the start of the hearing on Wednesday, presiding inspector Breda Gannon said she understood the concerns and difficulties expressed the previous day about the new information on temporary access routes that had been presented by EirGrid. She said she had decided to continue the hearing, the purpose of which was to act as an information gathering exercise to explore complex matters. She repeated her comments on the opening day, that the ultimate decision on the application rested with An Bord Pleanála, which would consider all matters raised and would have a number of options open to it. Her role was not to make a ruling on an item by item basis, she said. She invited observers and EirGrid to continue discussion on the construction module.

A lawyer for the NEPPC Michael O’Donnell BL said he had to accept the ruling but asked the inspector if she would agree to adjourn proceedings to allow an application to be made in court. This was rejected. The inspector said the NEPPC could continue to participate at any stage.

Robert Arthur of ESB International gave more details of the type of towers along the line, including a number of angle towers. Another ESBI consultant Jarlath Doyle explained details of the construction process, including the types of vehicles that would be used to bring concrete into fields where the steel pylons would be erected. It was also explained that ‘durabase’ matting was to be laid where necessary to provide access for vehicles in fields. These could be left in place for the duration of the construction process.

As an affected landowner with a pedigree Charolais herd on the family’s farm, Mary Marron of the CMAPC wanted to know if that meant the matting would be there for a span of three years. She called on EirGrid to be more specific about the fences that would be used to keep livestock away from the construction sites. Who was going to be responsible for the livestock and to whom could they address any queries relating to construction issues. It seemed that EirGrid was expecting each landowner to take responsibility for their animals and that was unacceptable.

Nigel Hillis of CMAPC pointed out that the type of fencing proposed along access routes was unsuitable for an agricultural setting. The pictures provided by EirGrid showed individual units of steel fencing joined together and anchored in blocks. He said such fencing was designed to keep people out, not animals and it would not stop a bull knocking it down. There was no proposal by the company to put up staked fencing with barbed wire, which is what farmers would use on their land.

Regarding the methodology used by the EirGrid consultants to investigate proposed access routes, Mr Hillis asked one of them if he had put on wellingtons and walked the dotted line shown on one of the maps leading to a proposed pylon site. He declined to answer the question. Some of his colleagues gave details later of how aerial photography combined with more recent Google mapping had allowed them to examine the possible routes, without having to contact landowners and access individual holdings.

Mr Hillis observed that the methodology of getting access to pylon sites was totally wrong. He explained that their committee had met on Tuesday evening and had decided they would not be returning as a group to the first part of the oral hearing.

Before departing Mary Marron said landowners should have been made aware of proposed changes. She asked EirGrid to provide proper photos of the type of machinery that would be used to access the pylon sites and asked for maps to show where matting would be laid. She requested the company to provide specific information on these issues.

Monaghan County Council senior planner Toirleach Gourley raised a number of questions with EirGrid about the details shown in some of the maps they had provided about the route of the line. He said the company had made an insufficient response to the concerns the Council had raised in their response to the planning application last August. Mr Gourley claimed a number of photomontages had limited legibility, such as one showing the point where the interconnector would cross the main N2 road at Annyalla.

A consultant landscape architect Joerg Schulze for EirGrid explained how he had drawn up the proposed route for the line, taking into account the relevant constraints such as avoiding residential areas where possible, sites of archaeological importance and loughs. In the drumlin landscape of County Monaghan it was not possible to avoid all drumlins but he believed he had found the best routing possible.

Mr Gourley said he was not convinced that putting pylons along the top of drumlins such as near Lough Egish was the ultimate choice. The planner also pointed out that Monaghan County Council had received no drawings showing the height and colour of the temporary buildings (portakabins) which EirGrid proposed to erect at a construction material storage yard beside the N2 at Monaltyduff/Monatybane outside Carrickmacross.

INTERCONNECTOR DAY4

Proposed Interconnector Vital for Society and Economy in North East: EirGrid

 Michael Fisher     Northern Standard

DAY FOUR

 This section dealt with the need for the development

Nigel Hillis addressed the oral hearing on behalf of the Co. Monaghan Anti Pylon Committee. He said up until now the group had never challenged the need for the project. But in the light of the unbelievable scrapping of the 400kV overhead line for Grid Link and the downsizing of Grid West to an alternative 220kV with multiple underground options they now had the right to and indeed must challenge the need for the project in its current form.

“How did EirGrid get it so very wrong with regards to those other two flagship projects. Can they now be trusted when they say that this project can only be delivered as an overhead 400kV line or is this all just a huge face saving exercise?” he said. “There is now no doubt that the need for this interconnector is not our need – it is Northern Ireland’s need”.

EirGrid’s Your Grid, Your Views, Your Tommorow states: “In the Re-examination of generation assumptions carried out in this update, the requirement for increased power to flow between Ireland and Northern Ireland in future years is confirmed. This is mainly driven by changes to the future all-island generation portfolio, plant retirements and the relative operational costs of generation plant in each jurisdiction.

The plant retirements referred to here are in Northern Ireland where very dirty plant must close down by 2021 and other, lets say, not quite so dirty plant must be restricted from 2023 onwards.

It is clear from the statements and speeches made by high level politicians and the Ulitility Regulator in Northern Ireland, in recent months, that panic has now set in regarding this situation which seemingly can only be addressed by the delivery of the North South Interconnector.

No provision is being made to address this security of supply issue within their own jurisdiction by way of replacing these dirty plants with modern clean ones. Indeed, the utterances and statements that have emanated from political, regulatory, business and economic commentators on both sides of the border but particularly from Northern Ireland, since this application was lodged with An Bord Pleanala, have been persistently vociferous to the extent that if this were a legal case it would be totally prejudiced at this stage.

This is clear proof that there is only one game in town with regards the need for the project and that is security of supply for Northern Ireland to prevent the “lights going out”. There is no talk about how it will be of mutual benefit to us down here – it’s all about Northern Ireland. Some of the statements have been hysterical to the extent that there would be a risk to life and limb in the absence of the Interconnector.

It would seem to us that all this has been a carefully orchestrated and choreographed effort intended to bring maximum pressure to bear on the respective decision makers and put them in a position whereby they could not possibly refuse permission.

I want to give you some examples of what I am talking about. EirGrid have often used the analogy of a three legged stool with regards to this development and the three legs are:

Security of supply; to facilitate increased renewable energy (mostly wind); to enhance the operation of the Single Electricity Market.

Security of supply

At the 2010 oral hearing EirGrid gave clear evidence that the security of supply in the North East region would be below acceptable standards by 2012. This was why there was a critical need for the sub-station at Kingscourt to link into the North East. In fact it was stated that even if planning permission for the interconnector was refused in Northern Ireland, the section from Woodland to Kingscourt would still be required to reinforce the North East. So it was with complete astonishment that in May 2011 less than a year after the previous oral hearing collapsed EirGrid stated in their Preliminary Re-evaluation Report that the sub-station at Kingscourt would not be required for at least 10 years. That would have brought us up to 2021 at that time. Their stated position regarding the sub-station in these application documents is the exact same – it will not be required for at least 10 years bringing us now up to 2026.

Will it ever be required? In March 2015 EirGrid published a series of consultation documents entitled “Your Grid, Your Views, Your Tomorrow”. A discussion paper on Ireland’s Grid Development Strategy.

In Appendix 1 entitled EirGrd Technical Analysis page 34 with regards to the North East region it states “The north east region has renewable energy resources and conventional generation sources. There is an excess of generation in the area”. The need for the sub-station in the Kingscourt area now seems to be an unanswerable question.

The renowned economist Colm McCarthy is on public record many times in many different forums, television, print media and public meetings as saying that Ireland is “awash with generating capacity” and any more whether it is wind, gas, biomass or whatever is simply not needed and makes no economic sense whatsoever.

How did EirGrid get it so wrong? In effect EirGrid applied to An Bord Pleanala in 2009 for permission under the Strategic Infrastructure Act for permission to construct a large 400kV sub-station that was not needed then, is not needed now and may never be needed in the future. But yet they built a technical and needful case for it at the oral hearing in 2010 that on the face of it could not be challenged. In fact, whatever about EirGrid’s record regarding public consultation and all the other discrepancies in the previous application no-one, at the previous oral hearing ever questioned their assessment of the need for the development or the sub-station – only the form in which it should be delivered i.e. overhead or underground. However this time the need for the development insofar as it is of benefit to this jurisdiction must be questioned.

A second link to Northern Ireland has nothing to offer us with regards to security of supply as they simply just want the interconnector to replace the old dirty generating plants that have to be retired. The CEO of EirGrid supported by his senior management team appeared twice last year in front of the Oireachtas Committee for Transport and Communications on the 21st April and 4th November.

The April meeting was specifically to discuss the North South Interconnector and the November meeting was to discuss Grid Link but ended up with most of the discussion on the North South Interconnector. At both meetings the one thing that the EirGrid could not explain to the satisfaction of the Committee members was why the proposed second interconnector needed to be rated at 1,500 MW. The big picture that the members of the Oireachtas Committee saw straight away was that there was already a double circuit 1,200 MW interconnector in place that could easily be upgraded to 1,500 MW. The existing Moyle interconector from Scotland to N. Ireland is rated at 500 MW. EirGrid’s own East West interconnector from Wales to Dublin is 500 MW and the new interconnector from France to Ireland is proposed to be 700 MW. Why did the second interconnector linking into Northern Ireland, which only has a peak daily demand of approx 1,200 MW, need to be rated at 1,500 MW.

The Oireachtas members did not question that there was a need for extra connectivity but they did robustly question the need for it to be at 1,500 MW. It did not make sense to them the need for effectively two interconnectors both to potentially carry 1,500 MW to link into the Northern Ireland grid that has no demand for anything close to that amount of power flow. It must also be said that Colm McCarthy, despite his opposition to any more generating capacity being built does recognise that there is a need for some sort of enhanced connection between Northern Ireland and Ireland, but nothing to do with security of supply down here.

If we have extra generating capacity down here then nobody wants to deprive our fellow citizens on the island from sharing in it to meet their needs and “keep the lights on”. However, the figures that I have seen would suggest that approx 400 megawatts of dirty plant will have to be retired but 250 megawatts of that will be replaced when the Moyle interconnector is repaired (on schedule of the middle of this year last I heard) which leaves a security of supply deficit of approx. 200 MW. Indeed EirGrid’s own graph bears this out.

Building a second 1,500 MW interconnector to address this deficit is like taking a hurley stick to swat a fly. This deficit could easily be addressed by a 500 or 700 megawatt HVDC underground cable laid along public roads which is one of the options for Grid West and was an option for Grid Link before it was scrapped altogether. It must be remembered that both Grid West and Grid Link were brought forward as 400kV 1,500 MW overhead lines to address the perceived need of both those major projects.

Now Grid Link has been scrapped and no line either overhead or underground is needed at all and Grid West can be downgraded to 220kV overhead line or an underground 500 MW HVDC cable. In this light it is right and proper to question EirGrid’s assumption that an overhead 400kV 1,500 MW line is needed. This has not been satisfactorily or clearly demonstrated. Unfortunately the question must be asked in the light of now no requirement for the sub-station at Kingscourt, in the light of the unbelievable volte face regarding Grid Link and the multiple options now on the table for Grid West – the question must be asked can EirGrid be believed regarding the need for a 1,500 MW interconnector?

This was the question posed by the members of the Oireachtas Commmittee last year and this is the question we are posing now at this oral hearing. We accept that there is a need for enhanced power flow into Northern Ireland but not at this level. Grid Link was initially proposed as a 400kV overhead line but that was not needed. Initially EirGrid proposed to underground it using VSC HVDC at a power rating of 700 MW costing 1.57 times the cost of overhead. And then it was scrapped altogether.

What is required here is an Interconnector defined by EirGrid as an electrical link, facilities and equipment that connect the transmission network of one EU member state to another. We would submit that the additional electrical link required to address the security of supply issue in Northern Ireland does not need to be 1,500 MW. Once this is accepted then other alternatives open up which will be addressed in the next module.

Renewables (wind)

Power lines are required to conduct electricity from one place to another on demand. It is a demand and not a supply driven system. Maybe smart grids and smart devices in home appliances may change that somewhat is the future but that is quite a long way down the road. So at present what we have is a demand driven power system and the available supply at any one time must meet the demand to, in EirGrid’s favourite colloquialism, “keep the lights on”.

Conversely it cannot be more than the demand or load will have to shed somewhere along the line. Unlike water it cannot be produced and stored in a large reservoir and drawn down as required. It must be produced in real time to exactly meet the demand. So on the island of Ireland we have a daily peak demand usually in that 5 – 7 pm time frame that must be satisfied and obviously a much reduced demand during the night hours.

The power that flows in the lines is normally a mix produced from various generating plants i.e the base load plants such as the coal burning Moneypoint, peat fired plants, the peaking plants such as gas, we have a little bit of hydro and of course wind. Hydro, wind and biomass are lumped in together under the heading of renewables but by far the biggest one is wind. The amount of wind in the mix obviously varies according to how windy it is but on my last electricity bill from ESB Networks it was 19.4% renewables which is mostly wind. I would hazard a guess that the full 19% was wind and the 0.4% hydro.

So, it does not matter in the slightest how much wind is available or none at all, whatever the demand is at that particular time of the day then that is all the electricity that is required. There may be the potential to produce twice the demand or even three times the demand but it cannot be produced because it cannot be stored to any great extent. Storage is what is referred to in the industry as the holy grail.

The only reason that an upgrade of a power line or a new power line is required is that wind has what is called priority dispatch. In other words because of CO2 targets wind energy must be prioritised and allowed onto the system to the greatest extent that can be safely accommodated without risking system failure. So for example in Grid West the need for the power line is allow priority dispatch to get the potential wind energy out of Mayo which the existing lines cannot carry.

Now of course in giving priority dispatch to wind means that other plant, invariably gas plants have to close down or more likely ramp down but still keep what is called a spinning reserve in order to come in again quickly when the wind dies down. It seems now that unless the wind farms in Mayo receive planning permission, bearing in mind that a large one has already been shot down by ABP, Grid West will go the way of Grid Link and not be required at all.

So in that regard it was very much a bespoke power line to cater for priority dispatch of wind from a single outlying area in Mayo. The planned overall wind energy production in the Mayo region was approx. 640 Megawatts, before this large wind farm was shot down. 140 Megawatts can be accommodated on existing 110kV lines and therefore the new line is required to carry 500 Megawatts. This is exactly the power rating of the HVDC underground option for Grid West. It is essentially a one way street.

With regards to the North South Interconnector there is no wind power in the midlands that requires any such bespoke power line to cater for wind. However as we have already seen there is the RIDP in the North West waiting in the wings, so to speak with a potential of up to approx 500 MW, much the same as Grid West, if it was fully developed between now and 2025. The RIDP as I have said is situated in the North West of N. Ireland and in Donegal and will require grid reinforcement which as Mr Fitzsimons pointed out last week has been superficially addressed in EirGrid’s Grid 25 SEA Implementation Report but only within the jurisdictional boundaries of the ROI.

The RIDP, if it is developed to its fullest extent, and I say if because there are obviously other factors in play here, has essentially nowhere to go without the North South Interconnector. So again this is very much the same scenario as Grid West – to get wind power from an outlying region to the market. However, it is unlike Grid West in this regard. If 500 megawatts of wind power from Mayo could be got onto the grid and I am not at all sure that it could for technical reasons. EirGird DS3. It would simply act like the East West Interconnector from Wales and just in simple terms shoot 500 megawatts up the line straight into the substation at Flagford. That is not what would happen with regards to the RIDP if 500 megawatts were to be produced from wind because due to the fact that it will be taken onto the existing grid, which has to be reinforced, as outlined in the SEA report, then a lot of that 500 megawatts would be disappeated onto the local grid before it got to the interconnector.

So, the point I am making is that regardless of where the power comes from only so much is required at any one time to meet demand and a second interconnector at 1,500 MVA is not required to meet demand nor is it required to meet priority dispatch of wind either from ROI or NI.

The Single Electricity Market SEM

The SEM went live on the island of Ireland in 2007. It is a pool system whereby all generators over 10 Megawatts come together in a wholesale market pool and essentially the retail providers draw out of that pool by what is called an order of merit. In other words the cheapest are taken first. Now on the face of it that seems like a good system except that every generator in merit gets paid the marginal rate. So how does this marginal rate work? EXPLAIN. There are approx 80 generators participating in the market pool etc.

And then we have wind energy – now wind does not participate in the pool because wind is free. Or so the wind lobby would have us believe. As we have already seen wind has priority dispatch and it gets paid at that marginal rate, the highest rate. So as more wind comes onto the system it will start displacing other generating plants, which may reduce the marginal rate because they will be taken off line from the top down. However, if the marginal rate drops too much then a floor price kicks in to support wind. It just depends what the marginal rate is at the time if there is any actual saving or not.

Indeed a recent report commissioned by IWEA dated March 2015 entitled the Value of Wind Energy to Ireland concluded that when all factors were taken into account wind was cost neutral on the system. This report concludes that wind generation will decrease wholesale prices, resulting in savings to the consumer, but will be offset by other system costs. The report states:

It is not transparently clear what proportion of EirGrid’s planned investment in the electricity network is required solely for the development of wind capacity. Nor has it been determined how the system services outlined in the DS3 program will be paid for. But if all these are passed through to customers, they offset the wholesale price benefit, meaning household and industrial electricity prices rise slightly”.

EirGrid say that there will be an immediate saving of €20 million per annum and rising over the years depending on various visions within the wholesale market. These forecasts have been reviewed by the CER and in evidence given to the Oireachtas Committee on Transport and Communications in June last year they said they were happy with at least a saving of €10 million. However, this saving is only in the wholesale market by way of “pass through” costs but the CER cannot guarantee that these savings will be passed through to the consumer in the final analyses. When energy prices started to fall dramatically in 2014 it eventually took a direct intervention by Minister Alex White to put pressure on the retail suppliers to ensure that even a small percentage was passed back to consumers by way of direct reductions.

In the UK the utility regulator Ofgem has referred the energy market to the Competition and Markets Authority CMA for a full investigation. In the light of this what confidence can the consumer have that any savings with regards to these hidden pass through costs will be passed back in any transparent and verifiable manner. I would confidently say absolutely none whatsoever. Remember these savings, if they actually exist at all are in the wholesale market and we are totally at the mercy of the half dozen or so retail suppliers to pass them back. Their track record to date in this respect is not encouraging to say the least.

In any event just to do some maths let us be generous and give the benefit of the doubt to the higher number €20 million. There are approx. 2.5 million electricity consumers (bill payers) on the island of Ireland. 1.8 in the South and 0.7 in the North. Just do simple arithmetic and divide €20 million by €2.5 million = €8 per year or 2 cent per day. We have just withdrawn the 1 cent and 2 cent coins because they were worthless. Take the average annual domestic electricity bill to be €800 – its actually around €900 but lets keep the maths simple. A saving of €8 represents 0.01% of the annual bill.

Let us do the maths another way. The value of the electricity market last year on the island of Ireland according to the SEMO website was €1,854,638,645. If my calculator is giving me the right answer then €20 million represents 0.01% of that market value. We have done the maths two ways and we get the same answer 0.01% saving and that is assuming it is even passed back. How do you see a saving of 0.01% on your electricity bill never mind verify it is totally beyond me.

These figures of €20 million rising to €40 million by 2030 that EirGrid and the Regulator in N. Ireland are bandying about may seen nice chunky figures but they are absolutely miniscule in the context of the overall market. Both Grid Link and Grid West were initially confirmed as 400kV overhead lines on the basis of long and extensive studies costing tens of millions.

Now the situation is that Grid Link as a 400kV 1500 MW line or indeed even as a 700 MW underground cable is no longer needed. What increased power flow can Series Compensation cater for? 200 MW 300 MW whatever it is then that was all that was realistically needed in the first place.

Likewise for Grid West when the need changed the options changed as well.

From our prospective there is no need for this development in its current form as we do not see any tangible benefits accruing to the consumers on this side of the border. It is not needed to “keep the lights on” down here. The scale of it is not required for renewables and in our opinion the savings are illusionary. If there is a need for it from Northern Ireland’s perspective, which there undeniably seems to be, then that need can be solved by underground cabling.

EirGrid’s statutory brief as they constantly remind us is to operate and ensure the maintenance of and, if necessary, develop a safe, secure, reliable, economical and efficient electricity transmission system, and to explore and develop opportunities for interconnection of its system with other systems, in all cases with a view to ensuring that all reasonable demands for electricity are met and having due regard for the environment;

Statutory Instrument 445 (2000)

We do not believe that this SI applies to Northern Ireland and we would contend that in that context all reasonable demands for electricity in this state are currently being met with absolutely no danger of the “lights going out” due to generation or transmission inadequacies in the foreseeable future.

A second interconnector of 400kV 1500 MW has not, in our opinion, been robustly justified to satisfy the need for the development which in our view is simply to get power into Northern Ireland to replace generating plants that must be retired to meet EU emissions legislation.

EIRGRID RESPONSE

EirGrid Manager of Transmission Network Planning Mark Norton told the oral hearing this afternoon (in response to the issues raised by observers) why the company needed to develop a second North/South electricity interconnector. Answering a question from Nigel Hillis of Co. Monaghan Anti-Pylon Committee, he revealed that the main flow on the interconnector operating at near its capacity (1100MW) would be for one to two hours per year.

Mr Norton explained why there had to be a sustainable solution for a long-term  economic benefit and provide flexibility for future regional and national development. If the network in the Republic was not meshed this way with the system in the North then there could be a system-wide loss of capacity if it was not built to cater for a 1500MW flow. It would instead be necessary to have multiple routes in order to match existing capability.

Mr Norton said that for long-term planning the interconnector would provide sufficient capacity for the market to make best use of the generation portfolio in both jurisdictions. It was the equivalent of building a motorway in order to cater for the traffic expected today and into the future.

The EirGrid representative said it would help to increase the network capability in the North East in order to meet demand and economic growth. Continuing the transport analogy he said it would act in the same way as a road by-pass, diverting power for the regions network. A high capacity line would permit the development of large-scale industry, he said.

In summary, Mr Norton said a second interconnector was required because modifying the existing smaller interconnector would not address future need. It would ensure security of supply. It would ensure an efficient single electricity market. It would integrate the generation of renewables. Finally, it would serve in the long term to reinforce the position of the North East area (of Cavan/Monaghan) in the Republic.

CMAPC CHALLENGE EIRGRID FIGURES

Nigel Hillis of County Monaghan Anti-Pylon Committee claimed that in his presentation Mr Norton had failed to show that EirGrid had provided a detailed cost benefit analysis for the project, taking all the facts into consideration such as the option for undergrounding compared to the costs of an overhead line. No details had been produced for example about the economic impact on tourism in County Monaghan. The type of analysis they had used was not a business model that would be sustainable in any other sphere, he said.

Mr Norton said that the semi-state company had complied with the statutory requirements and had looked at the wider impact.

Nigel Hillis asked Mark Norton about how often the proposed interconnector was to be used at full capacity for transferring electricity, 1500 MW in either direction S/N or N/S. Mr Norton explained that according to their modelling it would generally run up to 1100 MW total transfer capacity. When pressed by Mr Hillis how frequently it would be required at this level, the EirGrid representative revealed it would be between one and two hours per year. So on that basis (of one to two hours per year) EirGrid intended to construct a 1500MW high voltage interconnector, Mr Hillis said, adding that this was “unbelievable”.

BICYCLE FOR A MOTORWAY

A representative of the North East Pylon Pressure Campaign was also surprised at the revelation by Mr Norton. Colin Andrew used the analogy of EirGrid proposing to build a three-lane motorway for use by a bicycle.

NEPPC

Mr Andrew who is a chartered engineer said the group was not objecting in principle to the proposed EirGrid overhead electricity interconnector. But it was opposed to the technology applied, along with the associated giant pylons that would carve the heart out of the community in Meath, Cavan and Monaghan.

Colin Andrew told the presiding planning inspector Breda Gannon that over the past nine years since the project was initially made public, NEPPC believed EirGrid had singularly failed to demonstrate conclusively beyond any reasonable doubt the real need for the interconnector. This failure had involved contradictory statements more designed to provide arguments against counter proposals to use underground cabling or even alternatives such as the use of HTLS conductors on existing infrastructure.

Mr Andrew said an “open cheque book” proposal had been brought before the Planning Board that EirGrid could not cost as they had no land owner agreements and they did not know the cost of legal actions for devalued properties nor the costs associated with a vastly extended construction period due to access difficulties.

EirGrid have claimed that delay costs equate to €30 million per annum but refuse to accept that such annual costs are very likely to continue indefinitely as the project faces almost universal community and landowner opposition, until alternative technological proposals are presented to communities along the route.

Mr Andrew said the NEPPC believed that the need for the link had not been unequivocally demonstrated and thus any plans for such an interconnector were premature, ill-founded and unachievable.

Referring to EirGrid media and public statements about the ‘lights going out’ in the event of the delayed construction of the interconnector, Mr Andrew accused the company of scaremongering and being irresponsible. These scare tactics were being used to manipulate people into believing that life and limb would be put in danger if it did not go ahead.

He claimed that the second interconnector would be of no real benefit to the North-East area in the Republic. He also criticised EirGrid for failing to provide any economic model and hiding behind the veil of commercial sensitivity.

NEPPC contend that EirGrid have singularly failed to demonstrate that there is any strategic need or financial model that shows any form of cost-benefit analysis to justify this proposed interconnector and that technology exists to upgrade existing infrastructure, Mr Andrew said. This upgrading would offer substantial savings over the lifetime of the project resulting in significant reductions in power costs to the end user and being of significant benefit to the economy.

In conclusion Mr Andrew said the “open cheque book” approach by EirGrid to a “white elephant” project such as this was not only spendthrift but wholly unnecessary as it faced universal opposition from threatened communities and virtually all landowners. Thus the project even if permitted cannot be built as EirGrid have admitted. If the need really existed, then the only solution was to adopt underground cables or to upgrade existing infrastructure.

Earlier the hearing was told that the EirGrid plan is a key project forming part of the government’s energy policy. It would allow access to a wider electricity market in Europe and would bring benefit to all electricity users.

The overhead power line with up to 300 pylons in the Republic would run from Woodland near Batterstown in Co. Meath through part of Cavan and into County Monaghan, where 42 townlands would be affected. It would cross the border at Lemgare near Clontibret, into County Armagh and would terminate at Turleenan near the Moy in County Tyrone. The proposed interconnector would be in addition to the current double circuit AC 275 kV overhead transmission line that runs on a single set of pylons between the Louth sub-station in the Republic and Tandragee in Northern Ireland.

GOVERNMENT POLICY

Day four began with a section on the need for the development. The first person to address the two Bord Pleanála inspectors was Kevin Brady, principal officer in charge of strategic energy policy at the Department of Communications, Energy and Natural Resources. He said a green paper on Irish energy policy had been issued in May 2014. Ten weeks had been given for comments to be made in response and during that time 1250 written submission had been received. Four regional workshops had been held and the department had heard the views of a wide range of people including community groups, businesses and trades unions.

In accordance with EU energy policy a white paper on energy (Ireland’s Transition to a Low carbon Energy Future) was approved by the government in December last year, setting out a vision and framework for energy policy from 2015-2030. It set out the context of the significant role played by EU institutions in determining market regulations.

He said Ireland valued its relationship with Northern Ireland including energy matters and they were part of an all-island electricity market. Mr Brady said the need for an appropriate energy infrastructure including interconnectors underpinned all energy policy. But the government was not seeking to determine specific details of the interconnector.

EU energy strategy reiterated support for an all-island single electricity market and this was established in 2007. But the current system did not operate efficiently as there was limited interconnectivity between Ireland and Northern Ireland and it can’t operate as a single system, so it limits the benefits of the single electricity market. A second interconnected was necessary, he said, and this would lead to benefits to energy consumers across the island of Ireland.

The proposal had been designated as an EU project of common interest. They needed to ensure there was access to wider markets and both Ireland and Northern Ireland would benefit from security of supply by having a single system across the island.

EirGrid was the established national transmission operator. It played a key role in economic and social development, creating a modern (transmission) infrastructure. Effective management of it was critical to achieving Ireland’s strategic energy objectives.

In conclusion, the Department’s representative said the interconnector would help to reduce electricity transmission costs across the island and ensure competitiveness. It would ensure the efficient working of the single electricity market to the benefit of all users, offering access to a wider electricity market. It was a key project supported by government policy, Mr Brady said.

Nigel Hillis of the County Monaghan Anti Pylon Committee later welcomed a clarification from the Department of Energy representative. Kevin Brady said national policy does not seek to determine the specific details of schemes. The policy statement clearly states: “The Government does not seek to direct EirGrid and ESB Networks or other energy infrastructure developers to particular sites or routes or technologies”.the white paper on energy gave very clear direction regarding government policy. The department was very much involved in energy policy but it was not directing EirGrid regarding sites, routes or technology or where to draw lines on a map regarding the interconnector.

COMMISSION FOR ENERGY REGULATION

Next to address the hearing was the chair of the Commission for Energy Regulation, Gareth Blaney. He outlined the role of the Commission as a regulator. The CER is the independent economic regulator responsible for the natural gas and electricity sectors in Ireland. Its remit is to ensure the security of supply of Ireland’s electricity system and that Irish consumers have access to fair and reasonable electricity prices.

The CER is also a member of the Single Electricity Market Committee which is the body responsible for implementing and overseeing the electricity markets of Ireland and Northern Ireland as a single All Island electricity market (SEM), and thus must protect consumers across the island.

The CER reviews and monitors the expenditure of Eirgrid, which has a statutory role to develop the electricity transmission network, to ensure that these are delivered efficiently and so minimise the costs to the Irish and all-island consumer.

Mr Blaney said the regulator believed that the North-South Interconnector was an important development for the electricity network and would provide a range of benefits for the electricity consumers in both Ireland and Northern Ireland.

The interconnector would increase the security of supply of electricity against both long term and short term events. It would also help to reduce the wholesale cost of electricity on the island of Ireland, by allowing the system operator to have better access to the most efficient set of electricity generators for the whole island, benefitting both electricity consumers in both jurisdictions.

Mr Blaney said the lack of a second interconnector was a major constraint on the all-island system. This results in additional constraint costs that are borne by the all-island consumer.

The cost of this constraint would be in the order of €20m p.a. in 2020 rising to €40-60m by 2030. This figure was based on constraint costs alone and did not value the other strategic benefits from the development proceeding, including security of supply benefits.
In terms of numbers, the ESRI looked at this in 2013 and estimated that the new North-South interconnector would reduce wholesale electricity prices by 0.9% by virtue of being better able to schedule the most efficient or lowest cost generators.  Wholesale prices make up about half the electricity cost to consumers. On an average household bill of €1,200 per year that would equate to a saving of €6 per year.

Mr Blaney explained that the CER had approved an allowance for the expenditure on this project on the basis of the application EirGrid had submitted to An Bord Pleanála. “We will encourage EirGrid to ensure all transmission developments, including this one, is delivered in a cost effective manner”, he said.

On the basis of those benefits, the CER considered there was a clear need for the construction and commissioning of the North- South interconnector. Material delay of the North South Interconnector is, in our view, against the interests of Irish and all-island electricity consumers.

ELECTRICITY ASSOCIATION OF IRELAND

Chief Executive Owen Wilson spoke on behalf of the Electricity Association of Ireland, representing over 90% of electricity generation and supply activities and all distribution activities within the Single Electricity Market. Neither EirGrid nor SONI are members.

In considering compliance with EU and national policies, Mr Wilson said the development as proposed was confirmed Governmental policy, and was central to the delivery of a number of key government objectives in the field of energy and environment, in particular the maintenance of a single market. It was in the national interest both in terms of Ireland’s strategic economic and social development and Ireland’s relationship with a neighbouring state.

He explained that approximately 70% of electricity demand on the island lay east of a line from Cork to Belfast. The proposed development would provide the backbone for this corridor and create the opportunity to maximise the efficient development of renewable generation. It would also support growth in demand through substitution of fossil fuels by low-carbon electricity in line with the expectations of the EU.

In parallel with developments in energy policy the EU Commission has been undertaking a review of energy markets, including electricity. The review again highlights the critical importance of interconnection if effective balancing and intraday markets are to be established and the goal of a fully integrated energy market achieved. Legislation in this area is anticipated towards the end of this year, which will again reiterate the call for cross-border interconnections to be further developed.

Regarding complince with national policies, the EAI Chief Executive said documentation supporting the proposed development had highlighted the need for the project to support national energy and environmental policy in Ireland. The most recent reiteration of policy support for the proposed project had been given in the Energy and Climate White Paper published in December 2015. This commits the Government to promote and facilitate interconnection with other countries and regions and reaffirms the July 2012 Government policy statement on the Strategic Importance of Transmission and other Energy Infrastructure. This Statement specifically endorsed delivery of the North-South interconnector as Government policy.

With respect to Northern Ireland, the EAI said the development was in the strategic national interest of Ireland as it maintained and enhanced a critical relationship with a neighbouring jurisdiction. Non-delivery of the project or even delayed delivery beyond 2020 would have energy, environmental, economic and social policy implications for the North that were proportionately much more significant than those arising in Ireland. It would place a significant cost burden on Northern Ireland electricity consumers and taxpayers as the region attempted to meet its Renewable Energy Sources and Greenhouse Gas emission reduction commitments and maintain security of supplies locally.

Northern Ireland Ministers, policy makers and regulators have expressed with increasing frequency their concern and frustration at the delayed delivery of this infrastructure, the costs already being incurred as a result of this delay, the longer-term risk it poses to the security of electricity supply and affordability of that electricity and the consequences for more general social and economic development and the delivery of climate and renewables policy obligations in Northern Ireland.

The NI Utility Regulator commented in October at an EirGrid conference in Belfast that security of supply was becoming a dominant concern of the energy “trilemma” in Northern Ireland and emphasised that the North- South Interconnector must be delivered by 2021. In her view an underground solution cannot be delivered in sufficient time to avoid a real risk of blackouts. Her view has been endorsed by Minister Bell (DETI) who commented in December 2015 that “The requirement for this project is irrefutable as it is critical to long term security of supply for Northern Ireland.” and that “We all need to do everything we can to get behind bringing it to fruition”

In addition to the above, the previous comments in respect of European policy have similar effect in NI and the development of the proposed project will have equal benefit in this regard. While we in Ireland have time to make decisions on this proposal that luxury does not exist for our neighbouring jurisdiction whose future economic well-being is intimately linked to this project. EAI is of the view that a loss of trust by Northern Ireland policymakers arising from the delay or failure or delay in delivering this infrastructure risks significant damage to the national interest.

In terms of the need for this development from an industrial perspective I would like to draw the Board’s attention to a report published in January 2015 by EY “Powering the economy” which was commissioned by EAI. It noted that:
“The high quality of its electricity system plays an important role in the All-Island’s economic competitiveness. Surveys carried out by the World Economic Forum for their Global Competitiveness Report rank ROI and NI highly in terms of the quality of electricity supply compared to many other countries. The survey asked participants about the reliability of electricity supplies in their country, specifically in terms of supply interruptions and voltage fluctuations. The results show that the quality of electricity supply in the All-Island market is high.”

Using data from the updated 2016 WEF report, Ireland’s electricity system maintains its ranking at 17th among the 151 countries surveyed – ahead of Germany, Italy, and Spain and equal with the USA. The EY report also noted that two-thirds of indigenous and multinational companies view access to a high-quality electricity supply as ‘very important’ to their continuing operations in Ireland. This is reflective of Government policy in seeking to attract energy intensive, high-technology companies.

The proposed development enhances the robustness of the network infrastructure on the island ensuring the needs of the exiting industrial base continue to be met and maintains the relative advantage of both jurisdictions in attracting FDI.

The National Competiveness Council, which reports and makes policy recommendations to Government, notes in its latest Competitiveness Report published in December 2015 that: “Ireland remains a relatively expensive location for energy compared to most of our EU peers. Electricity costs are a particular issue for energy intensive sectors and many SMEs. Average SME expenditure on electricity amounts to 9 per cent of total non-wage costs”.

It further notes in respect of Grid 2025 that:
“it is important that investment to address key competitiveness gaps is prioritised and the investment is efficient.” adding that “Competitiveness, sustainability and security of energy supply are critical issues for Ireland and for enterprise. Achieving an appropriate balance between these three pillars requires the availability of an adequate energy infrastructure framework. It is important that such investment is at least cost and delivered in a timely manner.”

In its “Electricity Costs and Competitiveness Bulletin” published in June 2015 the NCC commented that:
“Changes in relative energy price competitiveness can have far-reaching effects on investment, production and trade patterns in internationally trading sectors, and directly affect the ability of enterprise to retain and grow output and employment.

The NCC recommended that: Policy should aim to deliver energy infrastructure investment at least cost: Ireland needs to ensure adequate network capacity to meet additional enterprise demand, especially in the main urban centres. This is particularly relevant for large, energy intensive manufacturing activity.

In the context of the NCCs commentary it is important to recognise that the electricity system in Ireland and Northern Ireland is structurally different in a number of respects from our competitors in Europe and elsewhere. These structural differences relate to the island’s remote geographical location and small size, topography unfavourable to hydro development and a geographically distributed population that increases the length of network required to serve customers. Our position in the investment cycle relative to international competitors is also a factor. All of the foregoing mean electricity prices are already structurally more expensive in Ireland and emphasise the need for cost efficiency in all aspects of the sector in support of national competitiveness.

The project as proposed will enhance and ensure into the future the quality and stability of the electricity network, improve system efficiency and reduce costs. IN so doing it will also improve the electricity price competitiveness of Ireland. Alternative measures do not provide the same level of quality, efficiency or cost saving.

Additionally, because of the relative ease and low cost of making new connections to the development as proposed along its route, the overhead line provides an easily accessible gateway in support of economic and industrial development in line with the BMW regional and county development plans for Monaghan, Cavan and Meath. The opportunity to access the proposed infrastructure becomes significantly more expensive and, consequently, of reduced value in terms of supporting such regional and local development, where underground cabling is used.

Home energy needs

The members of my Association engage with almost every household on the island. These companies are acutely aware of the weakened financial circumstances of a significant proportion of electricity customers, exacerbated by the recent severe recession. As an organisation we have put in place on a voluntary basis additional measures to support those customers experiencing difficulty in paying their bills.

I raise this point because we are not talking here about a small minority. The 2015 CSO Survey on Income and Living Conditions indicates some 16% of individuals suffer energy deprivation in Ireland rising to 31% for those at risk of poverty (income below 60% of the national median). Statistics are calculated on a slightly different basis in the UK, nonetheless the 2015 Annual Fuel Poverty report published by DECC indicates that while in the UK on average some 17% of households experience fuel poverty this rises to 42% in Northern Ireland. Thus a significant cohort of the population North and South have difficulties paying for energy today.

The Strategy to Combat Energy Poverty, published by Government in February 2016, highlights the significant consequences of fuel poverty for individuals and families, stressing in particular the negative health impacts of such deprivation and the additional strain imposed on the health services as a consequence. The Strategy specifically states that “the portion of energy costs that DCENR can control, i.e. those related to the delivery of Government policy on climate change and security of supply, need to be minimised as far as possible. This will involve ensuring that the energy market works for consumers, and that the distributional impact of policy decisions, which have an effect on energy costs, are assessed”.

Government Strategy notes that fuel poverty is a function of the thermal efficiency of dwellings, household income and energy prices. The proposed development, if constructed as submitted, will directly affect energy prices as it will deliver savings to customers from avoided costs in the order of €20m by 2020 and incrementing annually thereafter as a result of the more efficient operation of the electricity system on the island. It also has the potential to indirectly impact household income as it improves the competitiveness of the overall economy which in turn improves the employment environment.

As a consequence of the scale of the numbers of people affected by energy poverty and Government policy as articulated in the Fuel Poverty Strategy, it is appropriate for Eirgrid to ensure that the proposed project is delivered at the lowest practicable cost. This, in our view, is the case with the current application. Imposing additional costs can only exacerbate an existing challenging situation.

EAI suggests that the Board, in taking its decision in relation to this application, should also recognise the need for this project in terms of improving energy affordability for households and in particular the significant proportion of households affected by fuel poverty.

EAI wish to make a number of points In terms of the technical need for the project.

  1. The latest Generation Capacity Statement (2016-2025) published in February 2016 confirms that under all growth scenarios there will be a shortfall in generation capacity in NI from 2021 absent completion of the proposed development. This Statement incorporates the current out-of-market intervention by the Utility Regulator to assure supplies over the coming 3 years which is adding costs for consumers in Northern Ireland.
  2. An AC connection permits the full integration of NI and RoI networks and the additional system stability and supply security this provides. A less robust level of integration is delivered using a DC option.
  3. We note that current modelling indicates unconstrained flows in a meshed system of more than 1,000 MW. In our view this supports the scale of the proposed project and reflects a prudent assessment of future demand. In this context we would suggest that confidence in the demand forecasts is improved as a consequence of additional recent policy decisions including:
    1. The delegation of powers to adjust Corporate Tax rate to the NI Assembly which all policy-makers anticipate will add to economic activity and
    2. The impact of EU 2030 framework and related implementing measures on encouraging the provision of future energy demand in the heating and transport sectors from low-carbon electricity
  4. We are conscious that the capacitance factors place a physical limit on the length of underground AC cable nationally and are of the view this resource should be kept available for locations where public safety is an over-riding factor
  5. We reiterate our previous point that an OH AC option facilitates quick, low-cost tie-ins in support of local economic development along line route
  6. We are not convinced that the availability and average repair times for DC cable approximate to that of OH lines (it is too early to say given the very limited amount of cables installed in Europe to date and their age). This is relevant given the importance of enhancing security of supply as a feature of this development
  7. We are satisfied the development proposed by Eirgrid is in line with ENTSO-E standards.

The original evaluation of the regulatory authorities in 2004 still stands in that a strengthened meshed network on the island will best protect the interest of electricity consumers – which is their principal duty. Upgrading the exiting interconnector would assist in this regard, however this would not remove the risk associated with failure of a single line, including through physical damage. Given the social and economic importance of secure electricity supplies a physically separate second interconnector minimises this risk.

In conclusion, EAI members remain convinced that the development as proposed by Eirgrid fully respects Government energy, environmental, economic and social policy, supports the national interest in respect of Ireland’s relationship with Northern Ireland, meets the needs of affected regional and county development plans and is in the best interests of our domestic and business customers across the island.

 

PYLONS CONTROVERSY

ANTI-PYLON GROUP STEPS UP CAMPAIGN AGAINST EIRGRID PLANS FOR ELECTRICITY INTERCONNECTOR
Michael Fisher

EirGrid substation at Ballykelly, Co. Louth near Inniskeen for North/South Interconnector Photo © Michael Fisher

EirGrid substation at Ballykelly, Co. Louth near Inniskeen for North/South Interconnector Photo © Michael Fisher

A group representing landowners and householders opposed to EirGrid plans for an overhead North/South electricity connector that would be routed through south and mid Monaghan met last night to arrange a fresh campaign against the proposals. A public meeting has been organised by the County Monaghan Anti-Pylon Committee to be held on Monday April 20th at Aughnamullen Community Centre, Lough Egish. All of the county’s TDs and councillors are being invited to attend. Committee member Nigel Hillis told the Northern Standard their opposition to the plans was stronger than before.

Last week EirGrid’s Chief Executive Fintan Slye visited Carrickmacross as the company announced its new draft strategy for the future development of Ireland’s electricity transmission grid. It included updated plans for the North/South 400 kV Interconnection Development that would cross five counties from Meath to Tyrone.

EirGrid banner for North/South Interconnector Photo © Michael Fisher

EirGrid banner for North/South Interconnector Photo © Michael Fisher

EirGrid and its Northern counterpart SONI (System Operator for Northern Ireland) are jointly proposing a new high capacity electricity interconnector between the two networks. The draft strategy says there remains a clear need for the North/South Interconnector, and that the existing preference for a 400kV overhead line is still the most appropriate solution for the project.

The development would link a substation at Woodland, Batterstown in County Meath with a planned substation in Turleenan, in the Dungannon area of County Tyrone. EirGrid intends to submit a planning application for the North/South Interconnector in the coming weeks. Currently there is only a single interconnector, that runs past Ballykelly on the Carrickmacross to Dundalk road in County Louth (a few kilometers from Inniskeen)  to Tandragee in County Armagh.

Shane Brennan of EirGrid (right) points out the route of the proposed interconnector Photo © Michael Fisher

Shane Brennan of EirGrid (right) points out the route of the proposed interconnector Photo © Michael Fisher

At their public information office in Carrickmacross, SONI Eirgrid Project Manager Shane Brennan from Clontibret explained to me that the new interconnector would increase the capacity and reliability of interconnection between the two networks. It would allow the two independent networks to operate together as if they were one system, thus improving competition, and securing the electricity supply throughout the island of Ireland. EirGrid maintains that operating the two networks as if they were one system will bring cost savings for all electricity consumers as larger electricity systems can be operated more efficiently than smaller ones.

The increase in interconnection capacity will also facilitate the development of wind generation, which will help achieve Ireland’s renewable energy targets. Last November EirGrid submitted its draft application to An Bord Pleanála for review.  The following month, An Bord informed EirGrid that it has reviewed the draft and that certain specified missing information was required to be submitted. Last month EirGrid sent in further information, as requested.

EirGrid pylon at Ballykelly, Co. Louth near Inniskeen Photo © Michael Fisher

EirGrid pylon at Ballykelly, Co. Louth near Inniskeen Photo © Michael Fisher

Meanwhile EirGrid has re-published its proposed line route which will form the basis of an application for planning approval to be submitted to the planning authority in the coming months. This follows a review of the December 2013 line design. The review resulted in some of the proposed pylon locations being re-positioned along the proposed route, but the alignment itself was not changed.

Maps have now been made available showing the proposed route in County Monaghan. It takes in parts of Kingscourt, Co. Cavan, Magheracloone, Corduff/Raferagh then on to a controversial section around Lough Egish. The route continues to Drumhowan, Doohamlet, Annyalla and Clontibret where it skirts the battlefield site and then joins the Northern grid in County Armagh.

EirGrid has opened three project information offices, including one at the Workhouse in Carrickmacross where those with an interest can  call in and meet the project team. The Carrick office on the Shercock Road is open on Mondays and Thursdays 12 noon – 6pm.

EirGrid information office Carrickmacross Photo © Michael Fisher

EirGrid information office Carrickmacross Photo © Michael Fisher

According to Fintan Slye of EirGrid, there remains a clear strategic need for a second north-south interconnector.
“We committed last year, to be open with people and find out what it is they want from this most critical of infrastructure.  We are now asking people to give us their views on our draft strategy”, he said. Mr Slye concluded: “EirGrid must ensure the necessary grid is in place to ensure that Ireland remains competitive – fostering economic growth, attracting new investments, and supporting indigenous jobs. It must do this without placing too great a burden on communities, or too high a cost on industry. When we have received people’s feedback we will submit this draft to the Department of Communications, Energy and Natural Resources for its consideration before publishing the final strategy later this year.”

The County Monaghan Anti-Pylon Committee has been campaigning against the overhead route for the past seven years. It has argued that the lines should be placed underground. Nigel Hillis, an engineer, said the need for a new interconnector had not been identified by EirGrid and they had not persuaded people living in the affected area that it was needed. This was not the case with another major infrastructure development when the main N2 road was being improved with by-passes around Castleblayney and Carrickmacross.

He said there was still serious opposition to the plans. One of the main concerns from the start, he said, had been the scale of the project, because the size and topography of the small farms in the county had not been taken into account when the positioning of pylons was being worked out. He said EirGrid had not identified the need for having big pylons on top of hills, close to a farmyard or houses. (The company said the centre of the proposed high voltage line would be no nearer to a residence than 50 metres).

Mr Hillis questioned why EirGrid was suggesting that part of the proposed GridWest scheme (up to 30km) could be situated underground using trenches alongside roads. He claimed that people in Monaghan were being treated as second class citizens and said they wanted to be treated the same as others.

The Dáil Communications Committee chaired by John O’Mahony T.D. has invited EirGrid to appear before them in the coming weeks to answer questions about the North/South interconnector. Mr Hillis hopes his group will also be given a chance to put their views across as well. From the first day of their formation the committee had argued for an underground route and that was now feasible, he said, as this option was being considered for the other two major grid projects.

Eirgrid says there are technical issues with putting 400kV AC lines underground over long distances and there would be operational complexities. It maintains that underground cables for the North/South route would be too expensive and difficult to install. Local residents however think the cost to them, their livelihoods, their homes and to local tourism would be equally damaging.

Northern Standard Thursday April 9th p.31 with pictures by © Pat Byrne

Northern Standard Thursday April 9th p.31 with pictures by © Pat Byrne