INTERCONNECTOR LATEST

PLANNING INQUIRY ON EIRGRID NTERCONNECTOR TO HEAR VIEWS OF ELECTED REPRESENTATIVES

Michael Fisher

As the Bord Pleanála hearing into the proposed EirGrid North/South interconnector reaches the half way stage, public representatives will tomorrow (Monday) be asked to give their views on the development. A number of TDs from Meath and Monaghan along with local Councillors are expected to give evidence to the two inspectors in Carrickmacross. The oral hearing began on March 7th with an overview of the project and the views of the planners from the three counties involved. It’s expected to last a further five weeks, hearing mainly submissions from individual landowners.

EirGrid wants to erect a 400kV high voltage overhead line with 300 pylons extending from a substation at Woodland in Co. Meath near Dunshaughlin through part of Cavan and into Co. Monaghan, crossing the border near Clontibret. The Northern Ireland section of the line through Co. Armagh to Moy in Co. Tyrone is subject to a separate planning process. A preliminary public enquiry will be held in Armagh in June to assess the legality of the application by EirGrid subsidiary SONI.

The oral hearing got underway despite a legal move by anti-pylon campaigners to halt the proceedings. The presiding inspector said she was conducting an information gathering exercise and her report would be submitted at the end to the Planning Board for a decision.

In the third week of the hearing anti-pylon groups the NEPPC and Co. Monaghan Anti Pylon Committee withdrew from the proceedings, claiming they had become a farce. This was because EirGrid had added new information to the planning application submitted last June concerning 25 new or amended access routes out of a total of 584. These would be used by machinery carrying concrete and other material to the sites of the proposed pylons, mainly located in agricultural land. The hearing was told EirGrid had been granted access to only one quarter (25%) of the proposed sites in Meath, Cavan and Monaghan, owing to the strident opposition of local landowners.

Driving along some of the proposed route today the notices could still be found at various points such as Brittas, Donaghpatrick and Teltown in Meath (close to the historic Tailteann games site), as well as Shantonagh and Aughnamullen (Lough Egish) in Co. Monaghan, telling EirGrid staff or representatives to keep out of the fields. This meant the consultants for the semi-state company could not walk the ground and had to make use of other measures to draw up their reports on the proposed route, such as aerial photos, photomontages and views taken from the public road and ordnance survey maps, as well as Google earth material. There was some discussion about whether the photomontages taken at the Hill of Tara gave a true reflection of the impact of the line, which would be some 6km away from the historic site in the middle distance.

EirGrid told the hearing on day two that the temporary routes would not involve excavation or the laying of stones or wooden sleepers. Instead rubber mats or aluminium tracks would be laid on land required to gain access to 299 pylon sites.

Padraig O’Reilly of the North East Pylon Pressure Campaign said the hearing had developed into a charade second time round. A similar oral hearing on the interconnector six years ago ended when a discrepancy was shown in drawings including the height of the proposed towers in Co. Monaghan and EirGrid withdrew the application.

Meanwhile a legal action by the NEPPC, representing almost 200 landowners mainly in County Meath, went ahead at the High Court in Dublin. It is challenging the validity of the application. Mr Justice Humphreys is due to give a decision before May 12th on whether he will allow a judicial review.

Over 900 submissions comprising over 2000 people and some community groups were made to An Bord Pleanála. Most of them objected to the overhead power lines and pylons and called for them to be placed underground. The EirGrid project manager said last week the underground cable Direct Current (DC) option was the least preferred, primarily on the basis of cost effectiveness, its poor ability to facilitate future grid connections and because it would not be considered as complying with best international practice.

INTERCONNECTOR DAY16

This section dealt with material assets: general and traffic

Acting senior engineer with Monaghan County Council John McKernan said EirGrid’s response to submissions last year was too vague on a number of traffic issues. It did not provide any detail in relation to the transport of excess soil from the foundations of the proposed towers to the waste disposal sites. This was particularly in respect of egress from the access routes onto the public road, and the provision of visibility splays at the point of emergence onto the public road.

The response provided merely repeated what had been stated in the original application relating to the use of dumper trucks to deliver concrete to the foundations. He said the company’s response did not provide any detail regarding the off-loading of the concrete from the delivery truck at the public road, and the loading of the dumpers being used to deliver the concrete down the access lanes to the site of the towers.

Mr McKernan said no detail was given regarding the off-loading of the steel framework from the delivery truck at the public road and the loading of the vehicles being used to deliver the steel framework to the sites. EirGrid had still not addressed the key issues regarding the physical capacity of a number of the access routes to accommodate the traffic movements between the public road and the tower sites. He said no realistic measures had been provided to address the issues raised regarding any accommodation works and relating to the control of lands in order to carry out such works.

On the question of how much surplus soil and rock would be generated by excavation at the tower sites and taken away to a licensed waste management site, the ‘worst case scenario’ envisaged by EirGrid was said to be approximately 10,500 cubic metres. Mr McKernan said reasonable figures were required from the company in respect of waste soil generated at each tower location, in order to ascertain the volume of traffic movements generated on the affected public roads.

Regarding the frequency of construction traffic on narrow roads in Monaghan, Mr McKernan said concerns remained that a number of towers would be constructed at the same time in the same area, leading to a significant amount of traffic using the public road. He asked for specific details of the phasing of the construction work in order to allay the Council’s concerns.

Some of the haul routes were quite convoluted. No proposals had been put forward to prevent contractors using public roads that would provide more direct routes for access to towers. EirGrid had proposed to carry out a pre- and post-construction video survey of the road pavements and verges on the haul routes. But this was insufficient in his opinion and a full mechanical machine survey of the public roads involved should be made at least three months in advance of works commencing.

Finally, the use of flag men would not resolve difficulties regarding delivery trucks blocking the public road while parked for off-loading. Nor would it resolve conflicts between large delivery trucks meeting day-to-day traffic traversing the road.

Along with senior planner Toirleach Gourley Mr McKernan continued to interrogate EirGrid about when Monaghan County Council would be provided with specific foundation details for each of the 134 proposed towers in the county and part of Cavan near Kingscourt. EirGrid lawyer Jarlath Fitzsimons SC insisted the relevant information had already been provided in the application and response to submissions. Statements that there was inadequate or no information were without substance, he said. He told the presiding inspector it was not a function of Monaghan County Council to reject the information.

We are looking at new and significant information, Mr Gourley stated. It differed from what had been published in the environmental impact statement. He said he had identified gaps in the EirGrid information. As a result the Council could not examine the impact of construction vehicle movements such as concrete lorries on local roads. The latest information they received conflicted with the information presented on behalf of EirGrid yesterday.

Asked by the inspector about information on traffic movements and towers, consultant engineer Tom Cannon said there had been a robust traffic assessment and the figures provided were an over-estimation of what would be required. He said there would be excavated material during the construction of the proposed development, specifically in relation to the tower foundations. Typically 34 m3 of excess soil would be excavated at each intermediate tower location with approximately 230 m3 of excess soil excavated from angle towers. In the case of three angle 90 degree angle towers the excavations would be deeper, requiring more concrete to be laid and more soil to be removed. It was stated that 96 of the 104 intermediate towers would not require piling. A worst case scenario would be that all excavated material amounting to 10,500m3 for all the towers in Monaghan would be sent off-site to a licenced waste recovery facility. He indicated that there were a number of potential storage sites in Monaghan, including the proposed temporary yard outside Carrickmacross.

But senior planner Toirleach Gourley pointed out that because the licence was coming to an end at one site and another two had been filled with soil from the new factory development on the Monaghan by-pass, the possibilities for disposal were restricted. His estimate was that there was approximately 17,000 m3 of soil to be disposed off as there was an extra 7000 cubic metres intended for the storage yard over and above what was in the environmental assessment.

Jarlath Fitzsimons SC said EirGrid had used information that was publicly available at the time of the planning application in June last year. It was not possible to use a crystal ball to predict the possible landfill sites when the line came to be constructed. Mr Cannon, he said, had indicated some of the sites that might be available. There was a wide sweep of potential disposal areas provided. Different areas would be required at different times. Mr Gourley, he said, seemed to be arguing for perfection in the environmental impact statement.

Robert Arthur of ESB International repeated the various stages of construction that would be required for the towers and gave details of the timescale involved. John McKernan asked for details of concrete lorries that would be off-loading material on public roads to dumper trucks that would bring the concrete up to the site towers. Some of the roads were very narrow and one proposed point for off-loading was at a crossroads and another at a T-junction. He was informed there were three angle towers where extra deliveries of concrete would be required for the deeper foundation.

In response to further questioning, the EirGrid consultant Tom Cannon advised that where the same access route was being used for two or more towers, the pylons would be constructed one at a time in order to reduce the level of traffic on the public road. He outlined other mitigation measure that would be taken including the use of flagmen at a small number of locations to ensure that traffic was not blocked. He also said there would be one proposed road closure during construction of two towers in the Monaghan area.

Mr McKernan asked EirGrid to put in place a mechanical survey of the state of the local roads that would be used three months before the development started. Mr Cannon advised him that the company intended to do a video of the routes involved both before and after construction, but Mr McKernan said this would not be a suitable way of collecting and assessing the relevant information.

BALLOON FLIGHTS

Malcolm White of Irish Balloon Flights said his company had been providing passenger flights from its base in Co. Meath for sixteen years. He told the hearing about how their business could be affected if the proposed high voltage power line was permitted. Their main concern was for the safety of passengers and crew.

A consultant for EirGrid Damien Grehan said ballooning was taking place in a landscape that included numerous overhead cables including a 400kV line. Aeronautical engineer Rodney Fewings said the ultimate responsibility for flight regulation rested with the Irish Aviation Authority and pilots were allowed to fly over power lines.

The presiding inspector asked Mr Fewings about the potential of the overhead lines to impact on the Medevac helicopter operations in Ireland, as this had been raised in a number of submissions in response to the planning application. He said he saw no reason why it should be a problem because of the modern navigation equipment on board new helicopters.

This section dealt with the transboundary and cumulative impact

As members of the County Monaghan Anti Pylon Committee and NEPPC had decided a fortnight ago they would withdraw from the proceedings over EirGrid’s conduct at the hearing, it was left to the presiding inspector to ask EirGrid any relevant questions in this section. EirGrid said a comprehensive evaluation of the potential effects on County Armagh at the point where the proposed line crossed the border at Lemgare in County Monaghan had been set out in the environmental impact statement. These ranged from none to moderate.

EirGrid subsidiary SONI had produced its own impact assessment for the effects in the Republic of the development in Northern Ireland as the line extends to Turleenan near Moy in Co. Tyrone. Both companies together had produced a separate consolidated environmental statement on the entirety of the project.

BIRD STUDIES

EirGrid consultant ecolgist Daireann McDonnell who had presented details of the most recent wintering bird surveys for 2014/15 to the inquiry two days previously in response to a request from the National Parks and Wildlife Service then read a statement into the record. He confirmed that the studies along the proposed line had not identified any new sensitive locations or mitigation requirements for whooper swans. Mr McDonnell recommended that additional flight diverters should be installed on a section of the lines between thirteen towers near the River Blackwater in County Meath.

EIRGRID CLARIFICATION ON LANDS ACCESSED

The hearing was told EirGrid and its consultants had been able to gain access to only 25% of the land along the route required for the towers, because they did not have permission from every landowner. At the conclusion of the module EirGrid lawyer Jarlath Fitzsimons SC outlined the reasons why the company had decided not to use its statutory powers to gain access in order to carry out environmental appraisals.

He said EirGrid respected the rights of each landowner in relation to their own lands, and always sought to achieve access through liaison with landowners and local communities to the greatest extent possible. EirGrid and its team had conducted site appraisals at a sizeable number of locations which, given the high degree of uniformity of land type and land use in both study areas, assisted in the confirmation of the conclusions of the baseline environmental appraisals conducted without the benefit of site surveys, in many instances.

There was no necessity for EirGrid to exercise statutory powers inherited from the ESB in relation to conducting surveys of lands for the proposed interconnector because they were able to use a suite of alternative assessment methods. The senior counsel told the inspectors that EirGrid and its consultants were confident the appraisal methodologies employed where physical access to sites was not granted had not had a material impact on the quantity or quality or adequacy of the information included in both the Environmental Impact Statement and Natura Impact Statement submitted to the Planning Board as part of the application.

EirGrid remained of the view that the exercise of its statutory powers to gain access to lands compulsorily would have not resulted in additional information being garnered which would have altered the environmental appraisal in any material way, he concluded.

STAGE TWO NEXT WEEK

There is a chance today (Thursday) for interested groups or individuals to comment on part one of the proceedings, which began five weeks ago. On Monday the hearing moves into part two, when elected representatives, concerned residents groups from Co. Meath and then individual landowners will make oral submissions on specific issues. Dates for the hearing have been set until mid-May.

HIGH COURT CASE

At the High Court in Dublin last week Mr Justice Humphreys reserved a decision on a legal case by the North East Pylon Pressure Campaign. They are seeking permission for a judicial review of the validity of the planning application by EirGrid. The judge sad he hoped to give a decision before May 12th.

 

INTERCONNECTOR DAY12

This section dealt with human beings: tourism and amenity

Dympna Condra, tourism officer Monaghan County Council told the presiding inspector the proposed pylons and power lines would affect their ability to sell Monaghan as a tourist destination, especially for angling. Landscape and the natural environment were important elements in attracting visitors to County Monaghan. She pointed out that the development had the potential to impact adversely impact on tourism in Monaghan in general, owing to the visual impact upon the landscape.

A line of pylons constituted a visual intrusion on the landscape. The promotion of Monaghan as a destination for outdoor activities such as angling, walking, cycling, golf, horse riding and forest parks would be impacted by the proposed development, particularly in terms of visual impact.

ANGLING

The tourism officer said angling was an extremely important niche product for Co. Monaghan. The Council’s submission had outlined their concern about the visual impact in the Castleblayney, Ballybay and Carrickmacross lakelands area, and particularly at Lough Morne and Lough Egish. Their view was that this visual impact might adversely affect angling visitor numbers. She said EirGrid’s response that this was unlikely to prohibit activities continuing at these locations lacked detail as to how this conclusion had been arrived at, she said.

Dympna Condra pointed out that Monaghan County Council had invested hugely in the angling product in recent years, particularly, but not exclusively, at Lough Muckno. This had led to a huge increase in the numbers of angling tourists to Monaghan in the last three years, with Lough Muckno being the key attractor.

However, anglers tended to move around to fish at different lakes in the vicinity and the proposed development ran through a substantial part of this area. Lough Muckno has moved from having one or two dwindling angling festivals in 2012 to having twelve festivals scheduled for 2016, most of which attracted international anglers, who spread out to other lakes in the area. In addition, an angling festival is being revived in Carrickmacross and this would also augment the number of anglers to this wider area. In our experience over the last number of years, these were repeat visitors as Monaghan had a growing reputation for catering for the angling visitor.

IMPACT DURING CONSTRUCTION

EirGrid had stated that ‘whilst the visual effects of the construction of the pylons are assessed as being “temporary and locally significant” this would be unlikely to be significant for tourism owing to a number of factors. These included the generally transitory nature of tourists during an Irish rural holiday stay, moving between locations rather than remaining in one place for an extended period of time. Monaghan County Council maintains that this does not apply to the repeat angling visitor.

The tourism assessment by EirGrid was based on the general tourist market and an effort was made to locate the proposed development away from these facilities. However, the plethora of lakes in the Ballybay-Castleblayney area were key assets to the angling visitor and this did not seem to have been taken into account, according to the tourism officer.

Dympna Condra noted that it was Failte Ireland’s view that tourism factors (in particular the landscape) had been insufficiently developed in EirGrid’s assessment and that a further evaluation of the potential development on the landscape character of the area should be undertaken. She said the Council concurred with this view that tourism and landscape character were closely aligned. A group of angling journalists from the UK had visited Lough Egish last week making videos. So the visual aspect of the landscape was important for them.

The County Council’s submission to An Bord Pleanála last August pointed out there were a number of small lakes in this angling heartland. It expressed concern that the proximity of the line of pylons to some of these lakes might impact significantly on the angling amenity.

Lough Egish – this 117 hectare lake is a valuable pike fishery.

Lough Morne – this 45 hectare lake is a good game fishery and contains brown trout. Examples of other lakes in the general vicinity of the proposed line include:-

Corlatt Lake/Shantonagh Lake – these lakes drain into the Knappagh River and the River Annalee. It must be noted that the majority of these waters contain most of the coarse fish species with the exception of bream and tench but are regarded as very good pike fisheries.

Tonyscallon Lake – this lake covers an area of approximately three hectares and contains very good bream.

WALKING


The Monaghan Way is a 56.5km long distance walking route between Clontibret and Inniskeen. It is a stimulating combination of quiet country roads, cross country trekking, riverside walkways and lakeside approaches. Reflecting the Monaghan countryside, the walk mixes gentle sloping hill gradients with flat stretches of open countryside. There are no long or steep climbs and the route reaches a maximum altitude of 317m at the summit of Mullyash.

Eirgrid has accepted that along a 2km section of the Monaghan Way which runs parallel to and then crosses the power line route, walkers “will experience open views of towers at close proximity where there is no intervening vegetation, resulting in localised significant visual effects”. The tourism officer said this was a particular worry for those walkers choosing to start in Clontibret and it might have a significant impact on the numbers using the route.

Toirleach Gourley senior planner Monaghan County Council said there would be knock-on effects for visitors and on the landscape setting with its many lakes. He expressed fresh concern that two of the photomontages displayed by EirGrid showing the impact on the Monaghan Way at Lemgare Rocks near Clontibret and at Lough Morne near Lough Egish did not show the two most prominent pylons along the route which were both situated on high ground.

Brendan Allen a senior planner with ESB International said in making their assessment for EirGrid, they had identified the chief tourism assets in Monaghan from Failte Ireland records and the Co. Monaghan development plan, as well as various tourism websites. The Irish Trails website had provided them with information about the Monaghan Way which showed it started in Monaghan town and it was therefore described as being 64km in length. He said it had not been possible to obtain visitor statistics for the walking route, unlike many other trails where volunteer counters were used to compile the figures.

He said the environmental impact statement had acknowledged that fishing and angling tourism were important for Co. Monaghan. He told the hearing the setting of some of the lakes would be changed by the interconnector project. Regarding the impact of construction activity, Mr Allen said this would be broken up over short periods of time at various locations. The effects would pass over time, he added.

He said it was important to point out that in the route selection they had avoided the main tourism assets that were identified in the county plan. But it was not possible to avoid fully all tourism assets, such as the road where the power lines cross the Monaghan Way at Lemgare Rocks. Mr Allen said they had given due consideration to the visual impact at this point and at Lough Morne. According to the company, “any impact on local tourism resulting from the construction and operation of the proposed interconnector…must be considered in respect of the strategic need for and importance of the project, and the careful consideration of alternative routes.”

Tourism and leisure consultant Ken Glass for EirGrid said the impact statement had concluded that “the operation of the proposed development will not directly inhibit any tourist and amenity activities along its route.”

This section dealt with air (noise; vibration; climate)

An environmental health officer with Monaghan County Council Dermot McCague said they would have to discuss construction noise at the stage the pylons were being erected. He hoped they could come to an agreement with the developer to consult the Council about measures to be taken to reduce the impact on residents at each tower location. Work would be carried out during daylight hours and would have to be with the permission of the Council.

Barry Sheridan an acoustics consultant for EirGrid said the mitigation measures to be taken had been listed in the application and the response to submissions. It was predicted that the construction phase would result in a moderate, temporary and transient noise impact. Portable noise barriers would be used to screen the noise from machinery and piling work. Mr Sheridan was asked a series of questions by the presiding inspector about how the noise levels were measured.

The consultant explained the impact of operational noise on the power lines, such as turbulent wind noise (which occurred rarely on 400kV lines) and potential corona discharge. The latter became higher and might become audible in wet weather and in close proximity to the line. But on such occasions the background noise level of rainfall and wind tended to mask the noise from the transmission line.

EirGrid said no significant noise impact on animals was predicted to arise from the operation of the proposed line. Noise from the construction phase of the project would be similar to any other building site and should not cause any significant impact to livestock. Regarding operational noise such as gap sparking on the power lines, an equine specialist Michael Sadlier said most animals became habituated to noises. Once they realised there was no threat then they no longer responded.

A consultant occupational and environmental physician Dr Martin Hogan from UCC on behalf of EirGrid said the potential health aspects of noise had been dealt with in the environmental impact assessment. The standards and guidelines used in the appraisal were very stringent and designed to protect the most sensitive and vulnerable, he said. Dr Hogan was asked about the potential effect of the power lines on a person with autism. He said there was no real reason to suspect that people with ASD would be adversely affected by the project.

The hearing resumes this morning (Thursday) at the Nuremore Hotel in Carrickmacross with a module on cultural heritage. Officials from the Department of Arts, Heritage and the Gaeltacht are due to give their opinion about the impact of the interconnector on various sites in Monaghan, Cavan and Meath.

HEARING SCHEDULE

The presiding inspector Breda Gannon said she intended to continue the hearing on the following days (the schedule is usually posted daily on the Bord Pleanála website):

Week 5  Monday to Thursday  4th-7th April

Week 6 Monday to Thursday 11th to 14th April

Week 7 Monday to Wednesday 18th to 20th April

Week 8 Monday 25th and Tuesday 26th April

Week 9 Tuesday 3rd to Thursday 5th May

Week 10 Monday 9th to Friday 14th May (dates updated on 20/04/16)

HIGH COURT APPLICATION

The North East Pylon Pressure Campaign will today (Thursday) before Mr Justice Humphreys at the High Court in Dublin continue with an application for leave to apply for a judicial review. Lawyers for the group have twice requested the presiding inspector to adjourn the hearing. But she has decided to continue with what she described as an “information gathering” exercise and said she would be reporting back to the Planning Board.

 

 

INTERCONNECTOR DAY9

This section dealt with construction, including temporary access routes

At the start of the hearing on Wednesday, presiding inspector Breda Gannon said she understood the concerns and difficulties expressed the previous day about the new information on temporary access routes that had been presented by EirGrid. She said she had decided to continue the hearing, the purpose of which was to act as an information gathering exercise to explore complex matters. She repeated her comments on the opening day, that the ultimate decision on the application rested with An Bord Pleanála, which would consider all matters raised and would have a number of options open to it. Her role was not to make a ruling on an item by item basis, she said. She invited observers and EirGrid to continue discussion on the construction module.

A lawyer for the NEPPC Michael O’Donnell BL said he had to accept the ruling but asked the inspector if she would agree to adjourn proceedings to allow an application to be made in court. This was rejected. The inspector said the NEPPC could continue to participate at any stage.

Robert Arthur of ESB International gave more details of the type of towers along the line, including a number of angle towers. Another ESBI consultant Jarlath Doyle explained details of the construction process, including the types of vehicles that would be used to bring concrete into fields where the steel pylons would be erected. It was also explained that ‘durabase’ matting was to be laid where necessary to provide access for vehicles in fields. These could be left in place for the duration of the construction process.

As an affected landowner with a pedigree Charolais herd on the family’s farm, Mary Marron of the CMAPC wanted to know if that meant the matting would be there for a span of three years. She called on EirGrid to be more specific about the fences that would be used to keep livestock away from the construction sites. Who was going to be responsible for the livestock and to whom could they address any queries relating to construction issues. It seemed that EirGrid was expecting each landowner to take responsibility for their animals and that was unacceptable.

Nigel Hillis of CMAPC pointed out that the type of fencing proposed along access routes was unsuitable for an agricultural setting. The pictures provided by EirGrid showed individual units of steel fencing joined together and anchored in blocks. He said such fencing was designed to keep people out, not animals and it would not stop a bull knocking it down. There was no proposal by the company to put up staked fencing with barbed wire, which is what farmers would use on their land.

Regarding the methodology used by the EirGrid consultants to investigate proposed access routes, Mr Hillis asked one of them if he had put on wellingtons and walked the dotted line shown on one of the maps leading to a proposed pylon site. He declined to answer the question. Some of his colleagues gave details later of how aerial photography combined with more recent Google mapping had allowed them to examine the possible routes, without having to contact landowners and access individual holdings.

Mr Hillis observed that the methodology of getting access to pylon sites was totally wrong. He explained that their committee had met on Tuesday evening and had decided they would not be returning as a group to the first part of the oral hearing.

Before departing Mary Marron said landowners should have been made aware of proposed changes. She asked EirGrid to provide proper photos of the type of machinery that would be used to access the pylon sites and asked for maps to show where matting would be laid. She requested the company to provide specific information on these issues.

Monaghan County Council senior planner Toirleach Gourley raised a number of questions with EirGrid about the details shown in some of the maps they had provided about the route of the line. He said the company had made an insufficient response to the concerns the Council had raised in their response to the planning application last August. Mr Gourley claimed a number of photomontages had limited legibility, such as one showing the point where the interconnector would cross the main N2 road at Annyalla.

A consultant landscape architect Joerg Schulze for EirGrid explained how he had drawn up the proposed route for the line, taking into account the relevant constraints such as avoiding residential areas where possible, sites of archaeological importance and loughs. In the drumlin landscape of County Monaghan it was not possible to avoid all drumlins but he believed he had found the best routing possible.

Mr Gourley said he was not convinced that putting pylons along the top of drumlins such as near Lough Egish was the ultimate choice. The planner also pointed out that Monaghan County Council had received no drawings showing the height and colour of the temporary buildings (portakabins) which EirGrid proposed to erect at a construction material storage yard beside the N2 at Monaltyduff/Monatybane outside Carrickmacross.

INTERCONNECTOR DAY2

DAY TWO

This section dealt with the legal and statutory processes.  

Michael Fisher    Northern Standard

Esmond Keane SC for NEPPC told day two of the oral hearing in Carrickmacross that the North/South interconnector planning application by EirGrid was entirely invalid, fundamentally flawed and would be detrimental to landowners. He said EirGrid had not been given statutory power to construct the lines themselves and it was the ESB which had such power. So this was not a valid application from a person entitled to apply to carry out the development, he claimed.

The barrister said there was a possible conflict of interest in An Bord Pleanála deciding the planning application also being designated as the relevant authority in the Republic to manage an EU energy infrastructure Project of Common Interest. Referring to the environmental impact statement, Mr Keane said it failed to comply with what was required. There must be early and effective participation of the public in the consultation process. But this was utterly misconstrued by EirGrid. There had been no effective opportunity for the public to participate about how undergrounding of the power lines could be carried out.

Mr Keane said planning drawings showing proposed 400kV line pylons were utterly incomplete and inadequate. EirGrid said the towers ranged in height from 26m to 51m (80ft to 165ft). It was utterly inappropriate for members of the public not to be shown details of the insulators, conductors and points of connection for the towers in each area and how they related to their own homes. The drawings had failed utterly to give proper notice of what this development comprised of.

“One would have thought EirGrid on this occasion would have shown all the elements of the development and shown all elements of each tower at each location”, the barrister said. There was no idea from the drawings where a fibre optic cable mentioned in some of the documentation would go and if it would be strung between the pylons with the other wires.

Michael O’Donnell, a barrister representing Braccanby Irish Farm LLC and NV Irish Farm LLC in County Meath, told the hearing the entire basis of the planning application had been predicated on a fundamental error. It was not even clear who the applicant was because the construction work was purportedly to be carried out by the ESB, acting as an agent of EirGrid. He said the Planning Board was being put in an impossible position in deciding the application because it was also acting as the competent authority for a project of common interest.

EirGrid’s response was given by Brian Murray S.C. who confirmed that they were the applicants and all planning documentation stated this. So there could be no doubt who the applicant was. He explained that EirGrid exercised a close monitoring role regarding any construction carried out by the ESB on its behalf and such work was monitored by EirGrid engineers. EirGrid was the electricity system operator and was the proper applicant, he insisted. He said there was no legal inhibition on Bord Pleanála operating as a planning assessor and having a separate unit to consider PCIs.

EirGrid senior planning consultant Des Cox was asked by the NEPPC counsel Esmond Keane about arrangements for construction work around pylons and access routes. He explained that the temporary routes would not involve excavation or the laying of stones or wooden sleepers, but instead rubber mats or aluminium tracks would be laid on land required to gain access to pylon sites.

Asked if it would require the removal of hedges and the construction of entrances, Mr Cox replied that regarding hedges there would be a cutting down in some cases but not removal. Regarding a specific site near Kingscourt in County Cavan where the NEPPC claimed a new entrance would be needed, Mr Cox replied: “I do not know; I am not down at that level of detail”.

 

 

 

INTERCONNECTOR DAY1

BORD PLEANÁLA HEARING ON EIRGRID INTERCONNECTOR PLAN OPENS

Michael Fisher  NORTHERN STANDARD

A legal move by anti-pylon campaigners failed to halt the opening on Monday of a planning enquiry into a major project by EirGrid to construct a high voltage electricity line through Meath and parts of Cavan and Monaghan extending into Northern Ireland. Two inspectors from An Bord Pleanála began a hearing in Carrickmacross concerning the proposed North/South 400kV interconnector.

The hearing has been divided into two parts and it’s expected it could last up to three months. Over 900 submissions comprising over 2000 people and groups were made to An Bord Pleanála, most of them objecting to the overhead power lines and pylons.

DAY ONE

Project overview and views of the planning authorities.

The inspectors heard an overview of the project from EirGrid and brief submissions by planners from the three local authorities involved. But when the inspectors began the section dealing with legal and statutory processes, a challenge was made by a lawyer on behalf of the North East Pylon Pressure Campaign.

He asked the inspectors to adjourn the oral hearing because NEPPC had earlier in the day attempted to get it stopped at the High Court in Dublin. Judge Humphreys did not grant an interlocutory injunction but agreed to a review involving all parties on Friday 18th March. Senior planning inspector Breda Gannon said she intended to proceed with the hearing until such time as she received any court order to stop.

Sitting alongside another inspector Deirdre McGowan, Ms Gannon explained at the outset that this was an information gathering exercise for the Board. She said she would prepare a report and make a recommendation. The ultimate decision on the application rested with the Board, who she said might or might not approve it, with or without modifications.

This is the second such inquiry in over five years. A previous hearing in 2010 ended abruptly when a discrepancy was exposed in the planning documentation regarding the height of pylons and EirGrid withdrew the application.

INTERCONNECTOR PLAN

The high voltage line proposed by EirGrid would connect the electricity systems on both sides of the border. It would run for 103km from an existing sub-station at Woodland near Batterstown in County Meath, through a small part of County Cavan and through 42 townlands in County Monaghan. This section in the Republic would have 299 pylons ranging in height from 26m to 51m above ground level to carry the overhead wires. 165 of the pylons would be in County Meath, covering 54.5km and 134 in Cavan/Monaghan covering 46km of the line.

At Lemgare near Clontibret the line would cross into County Armagh and thence to Turleenan near the Moy in County Tyrone. This section is subject to a separate investigation by the NI Planning Appeals Commission, which will hold a one-day preliminary hearing in Armagh in June to consider legal issues.

PROJECT OVERVIEW

A barrister for EirGrid outlined why the semi-state company needed to construct the second interconnector. He outlined some of the technical reasons why the line was needed to balance the supply systems North and South.

Jarlath Fitzsimons S.C. told the hearing the project was essential to secure safe, reliable, economic and efficient electricity supply between the Republic and Northern Ireland. He said that an independent report by international experts in 2012 had estimated that undergrounding of the wires would cost three times more than putting them overhead. EirGrid was therefore proposing that the best technical solution was for a wholly overhead line.

He explained that the electricity markets North and South were interlinked and interdependent. If for any reason either accidental or deliberate the current interconnector was disabled then the consequences would be very grave indeed. If the imbalance caused by such an event was not corrected quickly then a system could collapse, he said.

Mr Fitzsimons said it was estimated the development would save €20m annually from 2020 rising to between €40m and €60m from 2030 onwards.

EirGrid senior planning consultant Des Cox explained the proposed route for the interconnector. Using maps he showed how the pylons had been sited in order to avoid residential areas where possible. Consideration was also given to avoid areas where there were important archaeological or geological features, and heritage interests. He said the application included a temporary storage yard for materials outside Carrickmacross.

MONAGHAN COUNTY COUNCIL

Toirleach Gourley a senior executive planner with Monaghan County Council said the EirGrid response to submissions published in December represented much of what was set out in the original application. A number of issues previously raised by the Council remained to be addressed, he said. He outlined some of these for the inspectors. Some of the detail about temporary access routes for the construction of pylons was quite limited.

Regarding photomontages that had been supplied by EirGrid, he said a number of these were not representative of the views at various locations and no new information had been provided to address this issue. Concerning roads, the Council still had concerns about the transport of excess soil from pylon construction sites to a waste disposal area and how it could impact on local roads that could not physically accommodate larger vehicles. The proposed video survey of roads before and after the erection of pylons was inadequate in terms of identifying any damage to them.

Mr Gourley said the Co. Monaghan heritage officer believed there was still insufficient information regarding the potential impact on archaeology and protected structures. The view of the council’s tourism officer was that the development will have an adverse impact on tourism in the county, in areas such as the Monaghan Way.

A senior executive planner for Meath County Council Fiona Redmond pointed out that since their submission last year commenting on the EirGrid application, the Council had approved in December a new county development contribution scheme 2016-2021 which came into effect on 1st January. She pointed out that the infrastructure charge for erecting a 400 kV pylon would be €10,000 per pylon to be paid by the developer.

CMAPC SUBMISSION ON LEGAL PROCESSES

The County Monaghan Anti-Pylon Committee was represented by Nigel Hillis. He told the inspectors EirGrid last week published its latest All Island Generation Capacity Statement 2016 – 2025. It stated that the second North-South interconnector was vital to ensure the security of electricity supply for the future in both Northern Ireland and Ireland.

“In association with the competent authorities in the respective jurisdictions, we are actively progressing work to deliver this Project of Common Interest by 2019”, the document said.

Mr Hillis observed that it was not clear from this if the competent authorities referred to were the competent authorities under the (cross-border) Project of Common Interest regulations or the competent authorities with regards to planning matters.

In any event it did not matter as there was only one competent decision making authority in this case, namely An Bord Pleanála. So therefore, EirGrid and An Bord Pleanála were actively progressing work to deliver this PCI.

Mr Hillis asked if this planning application had been prejudged. “Has the decision been made? Are we wasting our time coming to this oral hearing?”, he told the inspectors.

A lawyer for the North East Pylon Pressure Campaign requested that their submission on legal matters be adjourned until the morning as their senior counsel was not in a position to make a presentation, owing to his involvement that day with the case in Dublin.

Presiding Inspector Breda Gannon said the NEPPC was inconveniencing the hearing. She had allocated five hours for them to speak and in the circumstances she had no choice but to finish the first day of the hearing early. She penalised the group by reducing their allocated time to three hours when the hearing resumed on Tuesday morning.

INTERCONNECTOR

IMG_20160128_223901A Bord Pleanála oral hearing begins on Monday 7th March into EirGrid’s latest proposal for a North/South electricity interconnector, one of the largest ever infrastructure projects in the history of the state. Two inspectors from the Planning Board began hearing submissions at the Nuremore Hotel in Carrickmacross.

The plan proposes building 299 pylons in the Republic to carry a high voltage (400kV) power line from Woodland in Co. Meath where there is an existing substation to Turleenan near the Moy on County Tyrone. It would pass through Meath, a small part of Co. Cavan near Kingsport and then through 42 town lands in Co. Monaghan. The line is due to cross the border at Lemgare near Clontibret, beside Derrynoose in Co. Armagh. eirgridLogo

The line is a total of 135km long. The Northern Ireland section is subject to a separate planning application by EirGrid’s subsidiary SONI. It is under review by the Planning Appeals Commission, which will hold a preliminary public hearing in Armagh on June 21st to examine legal aspects of the application.

The Commission was requested by the NI Department of the Environment to conduct a public inquiry under Article 31(2) of the Planning (Northern Ireland) Order 1991 for the purpose of considering representations made in respect of the 2009 application. The inquiry opened on 6th March 2012 but was adjourned on 20th March 2012 when it came to light that the application and the environmental statement and its addenda had not been properly advertised in the press. The Commissioners recommended that before it was re-advertised, the environmental statement should be consolidated and updated to take account of changes put forward by the applicants in their evidence to the inquiry.

On 9th October 2014, the NI Environment Department renewed its request for a public inquiry into the 2009 application for the electricity interconnector proposal and asked that it be conjoined with an inquiry into the 2013 application for associated works. Copies of a consolidated environmental statement relating to both applications had previously been forwarded to the Commission. However, in a further letter dated 18th November 2014, the Department informed the Commission of the applicant’s intention to submit additional environmental information relating to the trans-boundary landscape and visual effects of the proposed development.

The Commission said it would take no further action in relation to the inquiry until:-       the additional environmental information had been submitted and the public consultation period had elapsed;
the Commission was provided with copies of all documents relevant to and arising from the additional information; and
the Department confirmed that it had in its possession all the environmental information it considered necessary to meet the requirements of the Environmental Impact Assessment Directive and Regulations.

System Operator for Northern Ireland welcomed the news that the PAC public enquiry would recommence in June. It said the North South Interconnector was required urgently for security of electricity supply in Northern Ireland. It said the proposed project would reduce electricity prices and provide Northern Ireland with a secure electricity supply by linking the grids in NI and the Republic.

After being referred to the PAC, the Public Inquiry hearing originally began in March 2012 and was subsequently adjourned to allow the submission of further information relating to the planning application. Having received all relevant information, the PAC has notified SONI that proceedings can now continue, a major milestone for the project as SONI’s General Manager Robin McCormick explained:

“We are pleased to have been notified by the PAC about the recommencement of the public inquiry into the North South Interconnector. It is a critical piece of infrastructure, essential for a secure supply of electricity for Northern Ireland. It will also significantly reduce the cost of electricity for consumers across the entire island and will allow us to increase our use of renewable energy, reducing Northern Ireland’s reliance on imported fossil fuels. SONI has worked tirelessly to progress the planning application to make these benefits a reality.

“The project is fundamental to the Northern Irish economy and is supported by DETI, the Utility Regulator and all of the main business organisations including CBI, Northern Ireland Chamber and Manufacturing NI, but, in order to keep the lights on and to avoid increasing consumer costs, the interconnector must be built by 2019 and to that end, we would hope for a speedy resolution from the inquiry.”

“We understand that some people have concerns, especially when it comes to large infrastructure projects of this nature. We have teams on the ground, listening and responding to those concerns and would like anyone with questions to know that we are available for discussions, up until the inquiry begins.”

SONI’s specially appointed Agricultural Liaison Officer Fergal Keenan, is available to provide information about the project and can be contacted directly at 07966-930844 or via email fergal.keenan@soni.ltd.uk.

ORAL HEARING IN MARCH ON INTERCONNECTOR

DSC_4296

Electricity Pylons beside a SONI/NIE sub-station in County Antrim  Photo: Michael Fisher

The controversial plan by EirGrid for a North/South high voltage 400 kV electricity interconnector with overhead lines on 400 pylons from Meath to Tyrone is to be the subject of an oral hearing by two inspectors from An Bord Pleanála in early March.

Fianna Fáil Senator Thomas Byrne confirmed that the Board is set to begin public hearing sessions from next March. The hearing is likely to be held over a twelve weeks period in Carrickmacross, where a previous oral hearing took place in May 2010.

Senator Byrne is one of a number of public representatives who are  strongly opposed to the project. He says he will be making a submission to the hearing to outline the serious concerns that residents in Meath have regarding the proposals.

“I’ve long held the view that this project is unworkable. There needs to be community consensus for the project and a far greater emphasis needs to be placed on upgrading existing infrastructure alongside ensuring that the new transmission line is placed underground,” said Senator Byrne.

“People in Meath feel that their concerns have not been taken on board by those pushing this project. They are not being treated equally as the development of new transmission lines in other parts of the country are proceeding with the lines being placed underground. However Meath residents are being told that the North South Interconnector has to be developed over ground. It’s unacceptable.

“Meath residents now have their chance to make their voices heard in relation to these proposals. I’ve been informed by An Bord Pleanála that the public hearing for the project will begin in March. I’ll be making a strong submission outlining why I think the proposals have to be cast aside. I encourage others with similar concerns to make a submission during the public hearings.

“In Fianna Fáil’s energy policy launched this year, we outlined that grid development such as planned under the North South Interconnector should be subject to a full economic review in light of our reduced energy needs. Fianna Fáil maintains that undergrounding the North – South Connector is the most preferential route along with upgrading existing infrastructure and this will form a key part of my submission,” concluded Senator Byrne.

Nigel Hillis of the County Monaghan anti-pylon committee said the fact the oral hearing is to take place has to be welcomed. He said a number of parties would be making a formal oral submission at the hearing. Formal notice of the hearing, including the agenda and the details of venue will be sent to all parties approximately two weeks in advance of the announcement.

In a letter to the 900 interested parties including individuals who made submissions (with a fee of €50) to the planning application submitted by EirGrid in June last year, An Bord Pleanála said that owing to the scale and complexity of the case, and the large number of written submissions received, parties are requested to indicate their intention to make a formal oral submission at the hearing, before 5.30pm on February the 4th.

Eirgrid Statement 

“We welcome An Bord Pleanála’s decision to convene an oral hearing and note that it is likely to commence in early March. Each aspect of this process is managed by An Bord Pleanála. We await further detail from An Board Pleanála with regard to the upcoming oral hearing. Our offices in Carrickmacross, Cootehill and Navan will continue to be open in the coming weeks for anyone who has queries about our application.”

EirGrid’s plans to build the overhead 400kV power line from Woodland in County Meath through parts of Cavan, Monaghan and Armagh to Turleenan near Dungannon in County Tyrone were lodged in June 2015. Observations had to be lodged with the planning authority in Dublin by 5.30pm on Monday 24th August. Over 900 submissions were received and because groups of people got together to lodge a single submission, the names of over 1500 were submitted, most of them opposing the plan and calling for it to be put underground.

Monaghan County Council was one of the prescribed bodies notified of the application.The planning department made a submission to the Board including comments made about the project by Councillors at a meeting. Cavan County Council and Meath County Council were also notified and the Cathaoirligh of each of the three councils including Councillor Noel Keelan of Monaghan have joined together to oppose the plans.

The Minister for Arts, Heritage and the Gaeltacht Heather Humphreys T.D. was notified along with her Cabinet colleague, the Minister for Communications, Energy and Natural Resources Alex White T.D. The Environmental Protection Agency, National Roads Authority, An Chomhairle Ealaíon, Fáilte Ireland, An Taisce, The Heritage Council, Irish Aviation Authority, Údarás na Gaeltachta, Health Service Executive, Commission for Energy Regulation, Inland Fisheries Ireland, Iarnród Éireann, Railway Safety Commission, Northern and Western Regional Assembly, Eastern and Midlands Regional Assembly and Irish Water were informed of EirGrid’s plans and given the opportunity to make submissions. Additional notifications were made to Birdwatch Ireland, Irish Peatland Conservation Council, and the North’s Environment Department.

According to the Bord Pleanála website, submissions were received initially from Dominic Halligan T.D. (Meath East, Labour), members of Meath County Council; Michael Halpin; Meath Farm Machinery, Navan; Sean Byrne; Cyril Darcy and family, Robinstown, Kells, Co. Meath; Noel Meade; Eugene Connolly; Fred Smyth; Navan Municipal District Councillors of Meath County Council; Scoil Bláithín Íosa, Ballynagearn N.S., Magheracloone and separately, All Saints National School Doohamlet and Doohamlet Childcare Ltd.; Patricia and Coleman Ryan; Hugh and Bernadette Duffy; Eamonn McNally; Irish Water; Kingscourt Stars GAA Club; Philip Smith; Michael Coleman; Fr Brendan Madden; Meath Cllr Ronan McKenna, Trim (FF); Meath Cllr Damien O’Reilly, Ratoath (FF); Meath Cllr Claire O’Driscoll, Ashbourne (FF); Brendan Doyle and Barbara Doyle; Eastern and Midland Regional Assembly; North and Western Regional Assembly; David Murray; Eugene and Rosemary Cunningham Corlea, Kingscourt; Meath Co Cllr Shane Cassells, Navan (FF).

The North East Pylon Pressure Campaign said it would continue to provide support to all individuals, groups  and organisations willing to make a submission and has been working closely with 97% of landowners who are in complete opposition to the planning application and who favour undergrounding.

When EirGrid made its submission in June to An Bord Pleanála, it contained detailed plans to erect over 400 giant pylons along the route of the interconnector. NEPPC says communities across the North-East are being discriminated against by Eirgrid and by the government because there is no underground option under consideration, unlike the Grid West and Grid Link projects. It says Eirgrid has changed nothing of any material relevance since 2007, when the project was first announced..

The grid operator for its part says an additional high capacity North-South interconnector will provide multiple technical and other benefits.  These include improving competition by reducing the constraints that are currently restricting the efficient performance of the all-island Single Electricity Market; improving security of supply and supporting the development of renewable power generation by enhancing the flexible exchange of power flows over a large area of the island. It says these benefits will accrue to all electricity consumers on the island of Ireland.

EirGrid has stated that the proposed interconnector will also provide sufficient additional transmission capacity in the North East area of Ireland to cater for growth in electricity consumption for many years and will also put the area in a good position if an even stronger economic recovery should emerge in the coming years.

The new interconnector will increase the capacity, and the reliability, of interconnection between the two networks. This will allow the two independent networks to operate together as if they were one system for the mutual benefit of residents and businesses in both jurisdictions.The increase in interconnection capacity will effectively eliminate current restrictions in cross border support in the event of a shortage of electricity in one jurisdiction, thus enhancing the security of electricity supply throughout the island of Ireland.

Operating the two networks as if they were one system will bring cost savings for all electricity consumers as larger electricity systems can be operated more efficiently than smaller ones. The increase in interconnection capacity will also facilitate further and greater connection of wind generation in both parts of the island which will help achieve Ireland’s renewable energy targets.

EirGrid’s counterpart in the North, SONI, also believes that the new link is vital to ensure the effective operation of an efficient all-island electricity market, to support the realisation of strategic renewable energy targets and to exert downward pressure on electricity prices for customers in Northern Ireland. It will allow the all-island wholesale electricity market to work more efficiently, enabling wider competition between power generators and electricity suppliers throughout the island, and therefore ensuring that future electricity prices will be as competitive as possible. It will enable more renewable generator capacity (mostly wind generation) to be connected to the electricity network. The governments in both jurisdictions have set challenging targets for the amount of electricity to be generated from renewable sources, 40% by 2020, and these targets cannot be met without additional interconnection.

2015 REVIEW

BOSENSp1

How I reported the closure of the Bose factory in January in The Northern Standard Photo: © Michael Fisher

Northern Standard  Thursday 7th January 2016

Michael Fisher looks back on some of the main stories of 2015:

BOSE CLOSURE

It was the first major story I wrote for the Northern Standard when I began covering the Carrickmacross area on a temporary basis a year ago. The news came out of the blue, creating shockwaves in Carrick that are still being felt.

In a statement of 290 words issued by a public relations company in Dublin, Bose Ltd. announced it was closing its County Monaghan facility with the loss of 140 jobs. It was probably just a coincidence that the news was released on a Thursday afternoon, the day on which this weekly newspaper is published. So the coverage had to wait until the following week. But this was a decision that had been taken some time beforehand at the company’s headquarters in the United States, where a plant in South Carolina was also being shut down.

DSC_0969.JPG

Workers at the BOSE factory in Carrickmacross react to news of the plant’s closure Photo:  Michael Fisher

What offended the workers most was the way the news was relayed to them. They were called into the canteen at 4pm that black Thursday (22nd January 2015) and by video link were addressed by the company President. They thought it was going to be part of the usual quarterly update on company performance. Instead they were being told they would be made redundant in April.

After lobbying by union representatives and local politicians, the date for the shutdown was postponed until the end of May, in the hope that some workers might be able to find alternative employment. Some like Pat McNally had been with the company since it was established by Dr Amar Bose in July 1978. The plant provided final assembly for select home cinema systems and Wave radios for the European market, and some remanufacturing for the region.

Councillors pressed the IDA to find an alternative employer but so far no replacement has been found, although some clients have viewed the premises. In the aftermath of the closure it was discovered that the factory premises was now owned by a private group, following new arrangements regarding IDA leases.

The last day at Bose (May 29th) was sad for all concerned. The workers came in small groups to collect their redundancy payments. The car park gates were locked and a few days later, the plant and machinery inside the building were put up for auction, bringing to an end a 37-year history of production at the site.

As they left the plant, the workers again pointed out that this had been a profitable operation for Bose, and their Irish base in Europe had never been affected by industrial disputes. They said they had always shown their loyalty to the company and had generally been treated well by their employer, until the founder of the company Dr Amar Bose had died two years ago.

In the words of the Carrickmacross-based Sinn Féin MEP Matt Carthy, the closure of the plant was devastating for the local economy and community who felt they had been let down by the government. It was the end of an era and a huge blow forthe whole of South Monaghan and beyond.

P1200321.JPG

Minister for Arts, Heritage & Gaeltacht Heather Humphreys T.D. congratulates Frances Treanor on her winning self-portrait Photo: Michael Fisher

TEXACO ART WINNER

In April an art student from County Monaghan won the overall prize in the Texaco Children’s Art competition. A great achievement by my neighbour, Frances Treanor from Drumdart, Tydavnet. The 18 year-old was rewarded with a trip to Tokyo to represent Ireland in an international art exhibition, along with a cheque for €1500. Her self-portrait drawing done in black ballpoint pen was part of the 16th International High School Arts Festival along with some other Texaco award winners. Back at her home in Tydavnet she told me about her experiences in Japan, a country she said she would return to if she got a chance.

Her five days there introduced her to Japanese food such as tempura (fish and rice) for which chopsticks were used. She was served dishes of sushi and sukiakki and also got time to do some sightseeing. This included areas such as Harajuku, the Meiji shrine and Takeshita-dori street. Frances also visited a rural area a few hours outside Tokyo and saw a red panda being fed in the zoo. She noticed that the streets were very clean, as well as being busy and hectic. Everyone was carrying an umbrella, Frances told me, and there were special holders at the entrance to the museum where visitors could leave them.

The winning self portrait was completed by her in two weeks and was described by the chair of the judging panel, Professor Declan McGonagle, as having been executed “with the skill and delicacy of a master”. The talented Frances had featured among the prizewinners in 2012 when she won second place in her age category for her work “Lighting Up the Imagination”. She is one of seven children and is studying art at the National College of Art and Design in Dublin, alongside her twin sister Maeve.

Frances was keen to thank her former art teachers at St Louis Secondary School in Monaghan, Teresa Mahony and Stephen Penders, who she said had always encouraged and developed her talent.

DSC_4296.JPG

Electricity pylons beside SONI/NIE sub-station in Co. Antrim  Photo: Michael Fisher  

EIRGRID PLANS FOR INTERCONNECTOR

EirGrid has begun a fresh attempt to get permission for a second North/South electricity interconnector. It would involve the erection of over 400 pylons carrying a 400 kV high voltage cable across five counties from Meath to Tyrone, including Monaghan. There has been strong opposition to the plan, with over 900 submissions to An Bord Pleanála since the new planning application was submitted in June. The Board is expected to make a decision later this year on whether to hold another public enquiry into the plan. More details of the EirGrid response to the submissions and objections can be found on p.14 and the Northern Standard will continue to report on this controversial issue in the coming months.

C-TEK CARRICKMACROSS

Computer-generated image of C-TEK Carrickmacross  Photo: O'Hanlon Property

Computer-generated image of C-TEK Carrickmacross Photo: O’Hanlon Property

C-TEK BUILDING NEARS COMPLETION

Michael Fisher  Northern Standard  Thursday 2nd July

The C-Tek building beside the Civic Offices will represent the new face of Carrickmacross when it opens in the coming weeks. This will give hope for the future, at a time when the town is still reeling from the loss of a major manufacturing facility, Bose, with the loss of 140 jobs. The team behind the development of this site hope it will bring the same success as the M-Tek building in Monaghan town, where a second similar building had to be added to meet demand.

The workspace, designed to attract start-ups and new companies, consists of a two-storey building, offering 10,000 square feet of space with nine units. A number of tenants have already been found. The idea for the project came about following a study which identified a need for modern workspace in Carrickmacross. Work began last August on the building which cost €1.4 million.

It’s hoped the workspace, which will have units ranging from 250 square feet to 1,000 square feet, will appeal to business start-ups and will attract anyone with new ideas.

Councillor Padraig McNally said the County Council were not looking for businesses that are long-established and are well able to pay the going rate. This would be very affordable accommodation, he said and every application would be decided on its merits. Up to now the schemes in both Carrickmacross and Monaghan were not being abused by long-established businesses, he said. He also pointed out that a start-up could mean someone who had been in business for five years but it could take twenty years before they were successful.

The building offers an opportunity to locate a business in a newly constructed modern office facility with outstanding features, location and flexibility. C-Tek (standing for Carrickmacross Technology Education and Knowledge) is designed and built to offer an enhanced commercial working environment in the town. It has been developed by Monaghan County Enterprise Fund and Monaghan County Council. The space offers new and established businesses an opportunity to move to a landmark building and pleasant working environment, complemented by modern facilities including excellent Information Technology infrastructure, dedicated fibre optic broadband, security, ample car parking and easy access to the town centre and main roads. It’s also an hour from Dublin and could appeal to business people in the greater Dublin area who are looking for start-up space or providing professional services.

It’s a two-storey building, with flexible size office suites available starting at 250 square feet up to 1,000 square feet. Its features include a high standard of construction, quality finish, elevator to first floor, high quality electrical and fibre optic cabling, canteen and toilet facilities.

Flexible lease terms, exceptionally keen rent and service charge.

Carrickmacross offers a wide variety of amenities and community facilities including shops, schools, sports, leisure clubs, hotels and restaurants. For enquiries, please contact Shane O’Hanlon of O’Hanlon Property on (042) 9662222 or mobile (086) 2374261 or email shane@ohanlonproperty.ie.